|
EC Białystok S.A
2008
|
Concept of a heat recovery
system from flues gas condensation for a 75 MW boiler fired with
biomass (fuel humidity approx. 40%). The study presented multiple
alternatives for the 13-15 MW system consisting of a scrubber and a
condenser recovering head for district heating. Technical solutions
were presented as well as location and connection of the heat recovery
system with flue gas ducts, DH system and raw water system. Technical
and economic analyses were made, as well as project profitability
analyses, taking into account environmental issues and grants.
|
|
Ministry of Science and Higher
Education
2008
|
Commissioned research project
PBZ-MeiN-4/2/2006, research task no. I.2.6/1 „Supercritical
coal units – use in cogeneration”Elsamprojekt
Polska participated in the project as a member of a consortium
consisting of Poland’s leading R&D institutions and
technical universities.In the study, a detailed analysis was made of
thermodynamic model for 400-800 MW ultra supercritical coal fired units
with and without CO2 capture by amine method. Optimisation analysis
were carried out, taking into account technical possibilities and
economic effectiveness of heat extraction from the unit and of heat
recovery from CCS system for district heating purposes.
|
|
Vattenfall Heal Poland
2008
|
Feasibility study of a biomass
unit for Siekierki CHP Plant. Analyses of multiple technical
alternatives for biomass in the form of wood chips and pellets,
gasifier, coal fired boiler conversion to biomass, construction of a
new biomass boiler, construction of a new biomass unit, biomass
handling systems for 50-300 thousand t/a biomass.
|
|
BOT Opole Power Plant
2007
|
Analysis of multiple
alternatives of using the auxiliary boiler for renewable power
production, including the modernisation of existing grate boilers, a
new straw fired boiled, a new wood chips fired boiler, a biomass
gasifier cooperating with the unit boiler, concept of including the
biomass boiler in the HP regeneration system of 370 MW unit; concepts
of biomass handling systems for wood chips, straw, pellets.
|
|
ZEW Kogeneracja S.A.
2007-2008
|
Consulting services in the
preparation and implementation phase of the project involving biomass
co-firing system for Wroclaw CHP Plant unit 1, including analyses to
select the best technical and economic alternative. The selected
alternative included co-firing dry biomass (pellets) with approx. 45%
energy input, in a pulverised fuel boiler OP230 and a biomass handling
system with silos and biomass transport to the boiler. An environmental
impact report was prepared for the project, as well as an application
for project development conditions. Technical specification was
prepared for tendering procedure for the modernisation of boiler OP230
and construction of biomass handling system.The documentation prepared
made it possible to select contractors and conclude contracts for the
project implementation.
|
|
Vattenfall Heat Poland
2007-2008
|
Analyses regarding the
possibility of constructing a new CHP Plant in Grudziądz municipality
(kujawsko-pomorskie province). The report presents the concept of a
coal fired 2x800 MW ultra supercritical power plant with an open
cooling system (water from the Vistula), and alternatively with a
closed cooling system with a cooling tower. A preliminary layout of the
plant in the area indicated by the Employer was made. External
conditions for the project in the suggested location were analysed,
including connection to the HV power grid, connection to the road and
railway systems, possibilities to take in and discharge post-cooling
water, collisions with airway routes. A preliminary analysis of railway
and truck transport for the new power plant was made, including
agreements with the Polish Railway regarding the construction of a
railway siding. A preliminary geotechnical analysis of the location was
carried out to determine the conditions for building settlement. A
preliminary environmental impact assessment was made for the new power
plant, including Nature 2000 and other protected areas. Taking into
account the analyses specified above, a general investment budget was
prepared for the green-field project with all the accompanying
infrastructure in the analysed location.
|
|
Vattenfall Heat Poland
2007
|
Feasibility study of a biomass
fired CHP plant in Pruszków near Warsaw. A number of
technical and economic alternatives were analysed for the forecast heat
demand of approx. 250MWt. Plant capacities from 30 to 70MWe were
analysed in various configurations such as one unit with one boiler,
one unit with two boilers, or two units. The study also included
biomass market analysis and possibilities of organising energy crop
plantations.
|
|
Gdańskie Przedsiębiorstwo
Energetyki Cieplnej
2007
|
Feasibility study of a
cogeneration unit with municipal waste and biomass as main fuel. A
number of technical and economic alternatives were analysed for a
forecast heat demand of approx. 100MWt. Main alternatives included:
Waste-To-Energy project based on unsorted municipal wasted and
alternatively energy fraction separated from waste and a biomass
installation. Biomass types analysed included straw, pellets and wood
chips.
|
|
ZEW Kogeneracja S.A.
2007
|
Study of biomass generation
unit at ZEW Kogeneracja S.A.”, aiming to find an optimum
technical and economic alternative for using biomass fuel for renewable
energy production at Wrocław and Czechnica CHP Plants.
|
|
Chemical PlantPolice S.A.
2006
|
Concept of fuel conversion
from fuel oil to natural gas for selected systems of Police Chemical
Plant. The work included technical and economic analyses of multiple
alternatives for fuel conversion from the currently used mazout and
light fuel oil to natural gas. Basing on the economic analysis, which
included investments costs, differences in the fuel costs and in the
related costs (such as operation costs, environmental costs,
maintenance costs), recommended alternatives were presented.
|
|
Vattenfall Heat Poland
2006
|
Preparing FGD plant concept
for Siekierki CHP Plant. A concept for FGD and a new chimney stack for
Siekierki CHP, for the existing coal-fired units and the planned new
unit, including analysis of several alternatives; preparing the
application and appendices for the application for issuing construction
conditions for the selected alternative; preparing tender
documentation, functional programme and the technical part of contract
specimen, necessary for public procurement procedure.
|
|
Vattenfall Heat Poland
2006
|
Analysis of possibilities of
constructing new units in Poland; the study analysed location
conditions for construction of new coal fired and CCGT units, analysis
of the existing energy sources and local heat markets, selection of
optimal locations for new generation facilities.
|
|
Vattenfall Heat Poland
2006
|
Pre-feasibility study for a
construction of a new unit in Warsaw. The analyses covered multiple
alternatives of power units from 200 to 700 MWe, sub- and
supercritical, of varied heal output. Analyses were made for two
possible locations, at Siekierki CHP Plant and at Kawęczyn Heat Plant.
Technical and economic optimisation involved incorporation of new
facilities into the existing process systems, in compliance with the
present and future environmental requirements. The analyses took into
account a number of parameters and conditions influencing the optimal
selection of recommended alternative, such as combustion technologies,
steam parameters, thermal cycle of the plant, concept of district
heating part, various cooling solutions involving an open cooling
system as well as dry and wet fan cooling towers, plant preparation for
the future requirements for CO2 reduction. Thermal cycles of the
analysed alternatives were modelled and analysed for a number of loads.
As a result of the analyses, supercritical coal-fired units were
recommended as optimum solution, for the location of Siekierki - 450
MWe net, for the location of Kawęczyn – 650 MWe.
|
|
Vattenfall
2005
|
Feasibility study of
installing heat accumulator tank at Żerań CHP Plant, WarsawThe study
investigated the possibilities of incorporating a heat accumulator in
the existing DH system at Żerań CHP Plant. Economic analysis was made
for a number of operation modes.
|
|
Vattenfall
2005
|
Technical and economic
analysis of installing a steam engine at CHP Pruszków. A
number of engine designs were analysed and economic analyses were made
for the selected alternatives.
|
|
Police Chemical Plant
2005
|
Pre-project study evaluating
economic viability of the projects involving modernisation of
turbine-driven compressors of synthesis gas and CO2 turbine in the
ammonia and urea production plant.
|
|
Radpec
2005
|
Full feasibility study of
waste incineration plant construction in Radom, according to The
National Fund for Environmental Protection and Water Management
(NFOŚiGW) requirements. Analysis of waste fuel availability, including
RDF and sludge; preliminary analysis of technical alternatives of the
waste-to-energy plant, producing heat and power in cogeneration
– selection of the most attractive solution; economic and
financial analysis of the selected alternatives.
|
|
Vattenfall
2005
|
Feasibility study of
installing heat accumulator tank at Siekierki CHP Plant, WarsawThe
study investigated the possibilities of incorporating a heat
accumulator in the existing DH system at Siekierki CHP Plant. Economic
analysis was made for a number of operation modes. Tender specification
for heat accumulator was prepared.
|
|
Białystok CHP Plant
2005-2006
|
Feasibility study of boiler
coal-to-biomass conversion at Białystok CHP Plant. The study consisted
of analysis of the possibilities of supplying timber biomass to
Białystok CHP Plant; technical-economical analysis of possibilities of
conversion; financial analysis of the investment; environmental impact
report to obtain environmental permits.
|
|
Atex Sp. z o.o
2005
|
Preliminary feasibility study
of a biomass-fired CHP project in Przemysl.
|
|
Elsam A/S
2005
|
Pre-feasibility Study of a
Biomass Fired CHP Plant (10-15 MWe with various cogeneration ratios.The
analysis covered a number of solutions for biofuels management and
logistics. Feasibility of installing a flue gas condenser to recover
heat for district heating was analysed as an additional option.
|
|
Elsam A/S
2004
|
Preliminary feasibility study
for a biomass fired CHP (20 MWe and 40 MWt) in the north of Poland.The
analysis covered a number of solutions for biofuels management and
logistics. Feasibility of installing a flue gas condenser to recover
heat for district heating was analysed as an additional option.
|
|
Elektrociepłownie Warszawskie
2003- 2004
|
Study on EW S.A. (present VHP)
development until 2020. The work included analysis of development
directions for VHP heat sources until 2020, taking into account
internal conditions as well as the changing external factors (such as
market conditions, environmental requirements etc.) For the purpose of
the study, a uniform dynamic technical and economic model of all heat
sources was prepared, including all VHP heat sources, split to
generation units. The model allows comparing the analysed development
alternatives. The technical model included efficiency data of the
existing and new equipment, minimum and maximum generation capacities
of turbines and boilers, fuel parameters, emissions and furnace waste
production, use of absorbent, water and other consumable media in the
existing and new flue gas cleaning installation as well as a dynamic
O&M model, taking into account operation hours, investment
costs and O&M costs. As a result of the work, possible
investment alternatives were presented, including environmental
installations for the existing facilities as well as construction of
new generation facilities, such as new boilers, new coal-fired CHP
units of various capacities, including a large supercritical unit,
combined cycle CHP units of 60-250MWe at various locations, small
biomass or multi-fuel CHP units.
|
|
Intercell
2003-2004
|
Concepts for long term energy
supply to secure Intercell energy demand.Technical condition of the
equipment was assessed, and a concept of constructing a new industrial
CHP plant of 50-100 MWe was presented. A number of fuel alternatives
and technologies were analysed, using coal or natural gas as primary
fuel. Each alternative included also applying waste biomass, sewage
sludge and waste wood for power purposes. Possibility of connection to
the national power grid was assessed.
|
|
Belchatow Power Plant
2003
|
Turbine Hall Equipment
Modernisation Concept Study for units 3-12 in 2007-2015. Technical
condition assessment. Modernisation proposals taking into account
available modern technologies and implications related to Poland
joining EU.
|
|
Elektrownie Szczytowo-Pompowe
S.A.
2001
|
Concept of a 22 MW wind farm
in Loznica, including feasibility study and a application for issuing
development conditions.
|
|
INTERCELL S.A.
2001
|
Analysis
of alternative heat supply for the paper factory by constructing an
industrial CCGT plant (approx. 30 MWe and 140 MWt) or a gas-fired heat
plant.
|
|
Łęczyńska Energetyka Sp. z o.o.
2001
|
Feasibility
study for an approx. 30 MWe CHP plant with CFB boiler at Bogdanka coal
mine, based on coal slurry, waste coal, sludge from sewage treatment
plant and municipal waste.
|
|
Legnica DH Company
2001
|
Verification
of feasibility study for converting the municipal heat plant in Legnica
into a CHP plant basing on the existing steam boilers, capacity of
approx. 10 MWe.
|
|
Opole
Power Plant
2000-2001
|
Technical and economic
assessment of “Technical conditions for Opole Power Plant
connection to Opole municipality DH network” issued by ECO
S.AThe analysis included influence of design temperatures, pressure and
regulation method (quality or quantity) on feasibility of supplying 200
MWt heat from 18K360 turbine extractions to DH network of Opole by a
planned DH pipeline of 9 km.
|
|
Vattenfall Poland
2000
|
Participation
in Tech-wise A/S study “Optimisation and development of
Warsaw district heating system”.
|
|
PAK Power Stations Group
1999
|
Ultra Super Critical steam
parameters. Optimisation study for Pątnów II Power Project.
|
|
Opole Power Plant
1997-1998
|
Rationalization and
availability studyELSAMPROJEKT made a review of company structure and
investigated possibilities of employment reductions at Opole Power
Plant so as to improve the organisation, operation mode and employment
following the example of a comparable foreign (Danish) power plant.
|
|
Undisclosed client
1998
|
Due diligence study for 10 MW
windfarm project in Poland. Activities included production estimate for
the windfarm, investment cost, energy pricing, ownership structure and
assessment of the economy.
|
|
Kobo
1998-1999
|
A feasibility study analysing
construction of a CHP plant (30 MWe, 60 MWt) with fluidised bed boilers
at Bogdanka coal mine, using waste coal from the mine.The study also
analysed the possibility to cover heat demand of neighbouring towns by
the new CHP plant.
|
|
Energoinwest Białystok
1998-1999
|
Feasibility study for
modernisation of Fasty CHP plant in Bialystok, covering usage of sludge
from the municipal sewage treatment plant as fuel for the boilers of
the CHP plant.The feasibility study will cover technical solutions as
well as economic and financial issues related to finding short term as
well as long term solutions for the CHP plant and the municipal sewage
treatment plant. Issues related to combustion of sewage sludge were an
essential part of the study.
|
|
ChełmZamojska
Spółka ElektroenergetycznaEastern Generation Ltd.
1998
|
Feasibility study of a CHP
unit for the city of Chełm. Analysed alternatives included a 60 MWe gas
fired combined cycle plant, as well as 60 MWe coal fired CFB and PC
boiler plants. The issue of utilising waste coal from the nearby
Bogdanka coal mine was discussed in detail.
|
|
Opole Power Plant
1997-1998
|
Analysis researching the
possibilities of introducing technical and organisational changes at
Opole Power Plant, to improve and rationalise its operation. The
coalfired power plant consists of 4 equal units with a capacity of
approx. 350 MWe and is one of Poland's most modern power plants.
Technical benchmarking with Danish power plants.Analysis researching
the possibilities of introducing technical and organisational changes
at Opole Power Plant, to improve and rationalise its operation. The
coalfired power plant consists of 4 equal units with a capacity of
approx. 350 MWe and is one of Poland's most modern power plants.
Technical benchmarking with Danish power plants.
|
|
Bełchatów II Power
Plant Management
1997
|
Independent expert opinion for
the study on super critical parameters and optimisation of unit
capacity for Bełchatów II.
|
|
Kostrzyn Paper MillVattenfall
PolandSp. z o.o.
1997
|
Feasibility study covering
rehabilitation of an industrial CHP plant at Kostrzyn Paper Mill.The
study covered analysis of heat and power demand and a technical
assessment of the existing equipment. The alternatives analysed
included combined cycle alternative consisting of gas turbines and
waste heat recovery boilers with supplementary firing, each with a
capacity of 70 ton/h steam.Preparation of full tender documentation for
modernisation of the existing and erection of two new gas fired
boilers. Tendering procedure and selection of Contractor.
|
|
Elektrociepłownia Zielona
Góra S.A.Danish Energy AgencyPartner: DPC.
1995-1998
|
Preliminary feasibility study
for modernisation Zielona Góra CHP Plant. The project was
grant supported by the Danish Energy Agency and co-financed by EC
Zielona Góra.The project included determining the heat,
steam and electricity demand. A number of plant concepts were analysed
such as biomass fired boiler and gas fired combined cycle plants. The
use of domestic low calorific gas was analysed. A combined cycle plant
with a capacity on 100 MWe based on domestic gas was analysed in
details covering technical, economic as well as financial matters
including defining security package covering off-take contracts.
|
|
Zespół Elektrowni
Ostrołęka
1994-1995
|
Feasibility study for
modernisation of Ostrołęka A CHP plant. The following alternatives were
investigated: rehabilitation of existing CHP, district heating
extraction from power plant Ostrołęka B, new coal fired CFB CHP, new
combined cycle gas fired CHP. The coal fired CFB and the gas fired
Combined Cycle plant were selected as the most attractive solutions and
detailed financial analysis were prepared for these alternatives.
|
|
Zespół Elektrowni
Ostrołęka
1995-1995
|
Pre-feasibility study of bark
firing at Ostrołęka A CHP Plant.The following alternatives were
investigated: new multifuel CFB boiler, additional furnace to the
existing boilers, new Bubbling Fluidized Bed (BFB) boiler, retrofit of
the existing PC boiler to BFB bark firing boiler. The latter
alternative was implemented. ELSAMPROJEKT prepared investment package,
and long-term fuel supply contract, implementation study, detailed
tender specification, and contract with main contractor.
|
|
Polskie Sieci
Elektroenergetyczne S.A.Danish Environmental Protection Agency
1993 - 1994
|
Technical Assistance to Polish
Power Grid Company (PSE)Preparation of a study "Potential of priority
and CHP Development in Poland" for the Polskie Sieci
Elektroenergetyczne (Polish Power Grid Company).In 1992 PSE agreed with
the World Bank to initiate a least cost plan for the development and
rehabilitation of the Polish power plants. Part of this study is an
analysis of the potential for development of cogeneration on the basis
of existing and new power plants.
|