Certificate 9444 QMS 2011O nasStruktura własnościZarządDziałyCo robimyUsługiWspółpracaUprawnieniaReferencjeStudium wykonalnościWykorzystanie biomasyWykorzystanie odpadówSpecyfikacja/PrzetargiAnaliza rynkowa; umowyAnaliza technicznaInżynier KontraktuDue diligenceOdziaływanie na środowiskoHeat accumulatorsBieżące projektyAktualnościKontaktPracaBiblioteka     Logo



Feasibility Study



Client/Year Project description
Synthos Dwory
Sp. z o.o. Oświęcim
2011 - in progress
Modernisation programme for Synthos Dwory CHP plant.
The work included preparing a concept for plant reconstruction in the form of several alternative investment programmes based on modernisation projects and construction of new coal or gas fired plants as well as reserve and peak load sources fired with various fuels (coal, natural gas, landfill gas, light fuel oil), several process heat demand scenarios (CHP capacity from 250 to 700MWt) and unit operation regime (full cogenetaion, partial condensing mode). Selection of the optimum investment programme was made basing on the most profitable process system, the fuel used and the reliability of heat supply to Synthos Dwory.

Dalkia Poznan
2011
Feasibility study for the construction of new CHP (ECIII) in Poznan.
The objective was to analyse the possibilities of new gas fired CHP plant construction, including a peak load heat source of approx. 65-80MWt, at the area of former Kopanina Heat Plant in Poznan. The analysed alternatives included construction of gas fired engines, gas turbines of approx. 6MWe and a 45MWe CCGT plant. The scope of work covered technical and economic analyses. As a result, technical concept of the new unit was presented as well as operation mode and economic viability of the project.

Dalkia Łódź S.A.
2011
Pre-feasibility study of CCGT construction at EC-2 Łódź CHP Plant.
The objective of the study was to analyse the possibility of constructing a CCGT unit at EC2 using the existing steam turbines. As a result of CCGT unit construction, coal combustion will be completely eliminated from the process. The scope of work covered technical and economic analyses. As a result, a technical concept of the unit was presented, with the operation mode and the economic viability of the project. After construction of CCGT unit, the CHP Plant is expected to have and output of approx. 200MWt and approx. 100 MWe.

Elektrociepłownia
EC Nowa Sp. z o.o. (Tauron)
2011
Modernisation concept for EC Nowa pumping systems.
The objective was to prepare an optimum concept for the modernisation of the pumping systems at industrial EC Nowa CHP Plant (120MWe, 1580 t/h steam), including piping, metering systems, control and instrumentation and power supply, in order to reduce power consumed by the pumping systems. The study presents the results of energy audit of the pumping facilities and a multi-variant concept of modernisation, indicating optimum solutions. The analysis covered feed water pumps, cooling water pumps, district heating water pumps and process water pumps. As a result of the study, an economically feasible modernisation concept was proposed, resulting in the total reduction of power consumption by approx. 32 GWh/a.

EDF Polska / Cergia
2010-2011
Advisory services to prepare the project of 120MWe/150MWt biomass/coal fired cogeneration unit construction in Torun for implementation.
As part of works, site analysis for the new unit was made, including the possibility of connecting to the existing technical networks and the limitations arising from environmental protection as well as formal conditions for the project implementation. Feasibility study of the unit with fluidised bed boiler fired with coal and biomass, taking into account operation of the existing generation facilities, was prepared. The feasibility study included detailed unit concept with auxiliary systems. Economic analysis including sensitivity analysis of the project was made.
The scope of work included preparing environmental impact report, application for environmental decision, application for the integrated permit, preparation of application to participate in CO2 emission trade system (ETS) and obtaining the permit, and preparing an application to connect the plant to the power grid.
Work also included preparing the concept for the tendering procedure to select the contractor(s) in two formulas: as turn-key contract (EPC) and in package-based formula.

EDF Polska / Kogeneracja
2010-2011
Advisory services to prepare the project of 120MWe/150MWt biomass/coal fired cogeneration unit construction in Siechnice for implementation.
As part of works, site analysis for the new unit was made, including the possibility of connecting to the existing technical networks and the limitations arising from environmental protection as well as formal conditions for the project implementation. Feasibility study of the unit with fluidised bed boiler fired with coal and biomass, taking into account operation of the existing generation facilities, was prepared. The feasibility study included detailed unit concept with auxiliary systems. Economic analysis including sensitivity analysis of the project was made.
The scope of work included preparing environmental impact report, application for environmental decision, application for the integrated permit, preparation of application to participate in CO2 emission trade system (ETS) and obtaining the permit, and preparing an application to connect the plant to the power grid.

Dalkia Łódź
2010
Feasibility study of the construction of heat accumulator tanks at Dalkia Łódź EC-3 (200MWe/830MWt CHP) and EC-4 (210MWe/860MWt CHP).
Technical possibilities were analysed of applying heat accumulators at the existing DH connection systems of EC-3 and EC-4, and the cooperation of heat sources in Łodz DH system including heat accumulation facilities (heat allocation). Optimum capacity of the heat accumulators was determined in the range of 10 000 m3 to 30 000 m3.
A technical and economic model of Łódź DH system was prepared, taking into account relation between the operation of EC-3, EC-4 and the heat accumulator. Economic analysis was made for various alternatives of heat accumulators’ operation and the cooperation of both CHP plants in ŁOdz DH system.

Vattenfall Heat Poland
2010-2011,
2011- in progress
Siekierki CHP boiler OP230 K-1 conversion to biomass fired BFB boiler. The project includes conversion of the boiler and implementation of biomass handling systems with the systems enabling deliveries of approx.. 320,000 t/a biomass by rail and by road.
A feasibility study was prepared to determine the project concept. The study analysed two solutions for boiler operation: common steam header with other boilers or as a separate unit (boiler + turbine set).
Concept of flue gas condensing system and biomass handling (320,000 t/a pellets) was described. Economic analysis of the project was made as a basis for optimising project alternatives.
The scope of work also included preparation of environmental impact report and an application for environmental permit and preparing an application for land development conditions, including permitting procedures and obtaining the said permits for the project.
The work also included preparation of tender documents (tender specification, contract) for two tenders: to select unit modernisation contractor and biomass handling system contractors, as well as participation in the evaluation and selection of contractors.

Vattenfall Heat Poland
2010
Feasibility Study: Analysis of a project involving construction of a gas fired unit at Żeran CHP Plant, Warszawa, including optimisation of technical and operational parameters.
The study included analysis of multiple project alternatives for the construction of CCGT unit of approx. 300-500 MWe and approx.. 250 MWt. Optimisation analyses were conducted, taking into account several sizes of gas turbines and CCGT units, in one-shaft and multi-shaft configurations, with backpressure stream turbine and with extraction/condensing steam turbine.
Thermal balances and a thermodynamic model using Thermoflex software were prepared.
An economic analysis of project profitability was carried out. Various operation modes were analysed depending on the change of power prices throughout the day and on the gas price structure. The analysis included operation of VHP’s other generating facilities.

ENERGA Elektrownie Ostrołęka S.A.
2009 - in progress
Preparing the project of Ostrołęka C Power Plant construction (first unit approx. 1000 MWe). The scope of work included the Concept Study including detailed feasibility study of the project and environmental documentation, as well as materials for the tender to select the Contractor for Ostrołęka C Power Plant construction.
As part of feasibility study, construction of new power plant with 1000MW unit (PF boiler fired with coal with up to 20% of biomass co-firing possibility) with a cooling tower. A financial and economic analysis of the project was made, as well as sensitivity analysis, risk analysis and business plan for the project.
The work also included support for the Client in the procedures related to the environmental decision for the project.
The scope of work covers also preparation of full Tender Specification (including draft Contract) for tendering procedure based on Public Procurement Law (negotiated procedure with publication), participation in negotiations and assistance for the Client during entire tendering process.

PGE Elektrociepłownia Gorzów S.A.
2009-2010
Technical study of biomass installation at Gorzów CHP Plant.
The study of OP-140 boiler conversion to biomass firing and construction of fuel handling system at Gorzów CHP Plant to produce renewable power.
The study includes different alternatives of biomass unit. Alternatives with wet and dry biomass were analysed. Conversion of existing PF OP-140 boiler from coal to biomass was analysed and new boiler was taking in to consideration as an alternative. Thermal calculations for the complete unit were carried out (boiler and turbine).

GPEC Sp. z o.o. (Stadtwerke Leipzig Group)
2009
Services of technical advisor in the project preparation phase for the construction of a new cogeneration plant fired with straw, to supply Gdańsk DH system.
The services included preparing a Feasibility Study, review of available aid financing sources and their mechanisms as well as analysis of straw acquisition possibilities and straw contracting for the project (including guidelines for logistics and sample contract).
Feasibility Study presented formal, technical and organisational conditions for the project. Three power plant sizes were analysed – approx. 26 MWe, 20 MWe, 15 Mwe, with respective biomass consumption of: 155,000 ton straw and pellets, 120,000 straw, 93,000 straw. Various plant configurations were analysed, such as using a reserve boiler house, applying flue gas condensation, using pellets or wood chipls as supplementary fuel, as well as various options of operation depending on the market conditions and the risk of biomass unavailability.
An economic and financial analysis was prepared, assuming two different financing options, with a sensitivity analysis.
An application for environmental decisions for the project was prepared, including project description and other required attachments.

El. Rybnik S.A.(EDF Polska)
2009
Review of technologies for biomass use in energy prodution and analysis of application at Rybnik Power Plant in order to increase biomass utilisation (Feasibility Study).
The objective of the study was to determine best technical solutions enabling the increase of biomass utilisation up to 700 000 Mg/a.
Multi-alternative concept analyses were made, taking into account co-firing various biomass types with coal in the existing unit boilers, as well as concepts of constructing a dedicated biomass firing installation (new boilers, biomass gasifier). Analyses covered biomass at different processing level, such as wet biomass, dry biomass, torrefied biomass, liquid biomass, straw in bales.
The study analysed issues related to biomass storage and logistics, including the existing transport limitations. Analysis of formal conditions for power to be qualified as renewable was made, as well as the analysis of metering and billing issues.

ZEW Kogeneracja S.A.(EDF Polska)
2009
Analysis of location conditions for construction of a supercritical condensing/CHP unit of approx. 450 at Czechnica CHP Plant.
The scope of work included analysis of location conditions for construction of a new condensing/CHP unit of approx. 450 at Czechnica CHP Plant. A supercritical unit with pulverised coal boiler was analysed, with wet FGD and catalytic DeNox system suitable for CO2 capture in the future. To determine the conditions of CHP construction and operation, a preliminary technical concept of the plant was prepared located at the land plot assigned.
The work included among other things analysis of the site and the conditions arising from current spatial arrangement and use of the land, environmental impact of the project, power grid connection, DH connection and conditions for CO2 storage.

Dalkia Poznan ZEC S.A.
2009
Technical and economic guidelines for PF OP-140(1K1) boiler conversion to biomass fired BFB boiler at Karolin CHP.
The study analysed the project involving modernisation of the unit with the conversion of PF coal fired boiler into biomass fired fluidises bed BFB boiler and construction of biomass handling system at Karolin CHP Plant, as well as turbine modernisation from backpressure to extraction-condensing. The analyses included a new chimney stack dedicated for the modernised boiler and analysed comparative solutions for FGD and SNCR plants. Main fuel after conversion is to be wood chips and non-forest granulate in the amount of approx. 230,000 t/a. A biomass handling system for the assumed types of biomass was proposed as well as a concept of unloading station, storage, crushing and transport to the boiler for the miscanthus straw.
The study included project profitability study.

PKN Orlen S.A.
2009
Preparing implementation of the project „Construction of 2x420-460MW near Anwil S.A. area in Włocławek”.
The works included preparing Feasibility Study analysing multiple alternatives for a two-phase construction of two CCGT units. Construction alternatives were presented. A closed cycle cooling system with cooling towers was analysed as well as an open cooling system using the Vistula river water. Technical and legal conditions for power plant construction were prepared. A preliminary concept for power export and gas fuel supply was presented, determining also the conditions of the local gas network operator. Economic analysis of the alternatives was made, basing on long term prices forecasts.
Guidelines for the Environmental Impact Assessment were prepared. General Investment Costs Schedule was prepared, together with the project budget. Project profitability analysis was also implemented.
Technical Appendix to Tender Specification for Turn-Key Delivery of CCGT Unit was prepared.

Dalkia Łódź S.A.
2009
Technical and economic guidelines for converting OP230 boiler to a biomass fired fluidised bed boiler at EC-4 CHP Plant in Łódź (biomass consumption 370,000 t/a.).
A detailed concept of boiler conversion was prepared with BFB furnace, technology of biomass combustion was presented together with installation parameters. Influence of modernised unit on the other Dalkia Łódź’s plants was analysed. Biomass transport and logistics assumptions as well as biomass handling system were prepared.
Analysis of economic viability of the project was carried out.

Dalkia Łódź S.A.
2008-2009
Feasibility study to determine optimum option to reconstruct generation capacity of EC2 (87MWe/578MWt). The study analysed using fluidised bed and pulverised fuel technology, basing on biomass, hard coal or gas. A technical concept of the proposed solution was prepared. As part of the study, analysis technical condition documentation regarding main buildings, equipment and systems of EC2 was made. A technical and economic model was prepared for the operation all three CHP plants of Dalkia Łódź as a part of Łódź district heating system. Alternative concepts of investments after shutdown of old generation equipment.
For the discussed investment alternatives economic effectiveness analysis was made.

Vattenfall Heat Poland
2007-2009
Feasibility study of biomass fired CHP Plant in Pruszków. Technical and economic analysis of multiple alternatives were made for the expected heat demand of approx. 250MWt. Plant sizes from 30MWe to 70Mwe, configured as one unit with one boiler, one unit with two boilers or two units were analysed. The option to applu a 3000 m3 to 20 000 m3. heat accumulator tank was also analysed.
The study also included analysis of the biomass market and possibilities to establish energy crop plantations.

Dalkia Łódź S.A.
2008
Technical and economic guidelines for biomass firing in steam boilers of EC-3 CHP Plant in Łódź (biomass consumption 85,000-300,000 t/a.).
A complex concept of EC-3 retrofit for biomass firing, including boiler modernisation and biomass handling. Technical alternatives of modernisation were analysed, including biomass co-firing with coal in OP-230 steam boilers, as well as conversion of OP-130 or OP-230 boiler to biomass firing (coal fired PF boilers conversion to fluidised bed boiler 100% biomass fired). The main biomass fuels analysed were pellets of agricultural or non-agricultural origin, as well as wood chips.
For the discussed technical alternatives analysis of economic viability of the project was made.

Vattenfall Heat Poland
2008, 2010
Preparing the concept of post combustion technology for a 450 MW–550 MW power unit.
Balance calculations were made for several ways of connecting CCS with the power unit and the existing system. The report included a preliminary CCS concept and proposed solutions for power supply, mechanical energy supply for main equipment drives and heat for the unit CCS system as well as waste heat recovery from CCS for district heating.
In 2010, update of the study was prepared, using up to date knowledge of CCS technology.

Vattenfall Heat Poland
2008
Preliminary feasibility study for a municipal waste incineration plant of 300,000 t capacity.
The concept included using the energy from waste and the plant operating as a CHP plant. The concept covered preparing the plant layout, waste reception system, boiler house with a flue gas cleaning and furnace waste handling. A cogeneration plant was analysed with different turbine solutions (CHP turbine, condensing turbine with heat extraction) and the resulting different values of power and hear production.
A comparative economic analysis of the considered solutions was made.

Vattenfall Heat Poland
2008
Long term development plan for Vattenfall Heat Poland CHP group in Warsaw and Pruszków.
Analysis of development directions for energy sources in Warsaw, taking into account the existing internal conditions and the changing external factors (legal, market-related, environmental etc). The report took into consideration the market situation in the city and in the country as well as performance data of the existing and new (planned) generation units, fuel characteristics, emissions and waste production, material wear etc. Modernisation of the existing facilities and generation units was analysed as well as the construction of new plants such as coal units, IGCC, Oxy-Fuel and gas units CCGT.
A comparative analysis of profitability was made for the selected alternatives, basing on the prepared technical and economic operation model for all the VHP plants operating as part of Warsaw district heating system. Benefits and risks were indicated for each alternative.
Profitability analysis was conducted, aiming in comparison profits and risks of all development alternatives.

EC Białystok S.A. (E.On Group)
2008
Concept of a heat recovery system from flues gas condensation for a 75 MW boiler fired with biomass (fuel humidity approx. 40%). The study presented multiple alternatives for the 13-15 MW system consisting of a scrubber and a condenser recovering head for district heating. Technical solutions were presented as well as location and connection of the heat recovery system with flue gas ducts, DH system and raw water system. Technical and economic analyses were made, as well as project profitability analyses, taking into account environmental issues and grants.

Vattenfall Heat Poland
2008
Feasibility study of a biomass unit for Siekierki CHP Plant. Analyses of multiple technical alternatives for biomass in the form of wood chips and pellets, gasifier, coal fired boiler conversion to biomass, construction of a new biomass boiler, construction of a new biomass unit, biomass handling systems for 50-300 thousand t/a biomass.

Poland’s Ministry of Science and Higher Education
2008
Commissioned research project PBZ-MeiN-4/2/2006, research task no. I.2.6/1 „Supercritical coal units – use in cogeneration”
Elsamprojekt Polska participated in the project as a member of a consortium consisting of Poland’s leading R&D institutions and technical universities.
In the study, a detailed analysis was made of thermodynamic model for 400-800 MW ultra supercritical coal fired units with and without CO2 capture by amine method. Optimisation analysis were carried out, taking into account technical possibilities and economic effectiveness of heat extraction from the unit and of heat recovery from CCS system for district heating purposes.

BOT Opole S.A.
2007
Analysis of multiple alternatives of using the auxiliary boiler for renewable power production, including the modernisation of existing grate boilers, a new straw fired boiled, a new wood chips fired boiler, a biomass gasifier cooperating with the unit boiler, concept of including the biomass boiler in the HP regeneration system of 370 MW unit; concepts of biomass handling systems for wood chips, straw, pellets.

ZEW Kogeneracja S.A. (EDF Polska)
2007-2008
Consulting services in the preparation and implementation phase of the project involving biomass co-firing system for Wroclaw CHP Plant unit 1, including analyses to select the best technical and economic alternative.
The selected alternative included co-firing dry biomass (pellets) with approx. 45% energy input, in a pulverised fuel boiler OP230 and a biomass handling system with silos and biomass transport to the boiler. An environmental impact report was prepared for the project, as well as an application for project development conditions. Technical specification was prepared for tendering procedure for the modernisation of boiler OP230 and construction of biomass handling system.
The documentation prepared made it possible to select contractors and conclude contracts for the project implementation.

Vattenfall Heat Poland
2007-2008
Analyses regarding the possibility of constructing a new CHP Plant in Grudziądz municipality (kujawsko-pomorskie province).
The report presents the concept of a coal fired 2x800 MW ultra supercritical power plant with an open cooling system (water from the Vistula), and alternatively with a closed cooling system with a cooling tower. A preliminary layout of the plant in the area indicated by the Employer was made. External conditions for the project in the suggested location were analysed, including connection to the HV power grid, connection to the road and railway systems, possibilities to take in and discharge post-cooling water, collisions with airway routes. A preliminary analysis of railway and truck transport for the new power plant was made, including agreements with the Polish Railway regarding the construction of a railway siding. A preliminary geotechnical analysis of the location was carried out to determine the conditions for building settlement. A preliminary environmental impact assessment was made for the new power plant, including Nature 2000 and other protected areas. Taking into account the analyses specified above, a general investment budget was prepared for the green-field project with all the accompanying infrastructure in the analysed location

Gdańskie Przedsiębiorstwo Energetyki Cieplnej (Stadtwerke Leipzig)
2007
Feasibility study of a cogeneration unit with municipal waste and biomass as main fuel. A number of technical and economic alternatives were analysed for a forecast heat demand of approx. 100MWt. Main alternatives included: Waste-To-Energy project based on unsorted municipal wasted and alternatively energy fraction separated from waste and a biomass installation, as well as heat accumulator with capacity of approx. 8000 m3. Biomass types analysed included straw, pellets and wood chips.

ZEW Kogeneracja S.A. (EDF Polska)
2007
Study of biomass generation unit at ZEW Kogeneracja S.A.”, aiming to find an optimum technical and economic alternative for using biomass fuel for renewable energy production at Wrocław and Czechnica CHP Plants.
In the study functionality of heat accumulator with capacity of 2000-3000 m3 was examined mainly for levelling of irregularity of heat consumption by green house.

Vattenfall Heat Poland
2006
FGD plant for Siekierki CHP Plant in Warsaw.
The scope of work included preparing a concept for FGD and a new chimney stack for Siekierki CHP, for the existing coal-fired units and the planned new unit, including analysis of several alternatives. The study compared the FGD concepts based on wet lime technology, semi-dry method and dry method. As a continuation of the conceptual work on multiple alternatives, a detailed FGD concept for coal fired boilers at Siekierki CHP was prepared.
Works included preparing the application and appendices for the application for issuing construction conditions for the selected alternative. Tender Specification was also made for FGD system with two absorbers for 8 boilers, for 3.1 million Nm3/h, including functional programme and the technical part of the contract with appendices necessary for public procurement procedure.
FGD system at Siekierki is currently under construction.

Vattenfall Heat Poland
2006
Analysis of possibilities of constructing new units in Poland; the study analysed location conditions for construction of new coal fired and CCGT units, analysis of the existing energy sources and local heat markets, selection of optimal locations for new power plant of 500-2000 MW. Sites at the existing power plants were analysed as well as green field locations.

Vattenfall Heat Poland
2006
Pre-feasibility study for a construction of a new unit in Warsaw.
The analyses covered multiple alternatives of power units from 200 to 700 MWe, sub- and supercritical, of varied heal output. Analyses were made for two possible locations, at Siekierki CHP Plant and at Kawęczyn Heat Plant. Technical and economic optimisation involved incorporation of new facilities into the existing process systems, in compliance with the present and future environmental requirements. The analyses took into account a number of parameters and conditions influencing the optimal selection of recommended alternative, such as combustion technologies, steam parameters, thermal cycle of the plant, concept of district heating part, various cooling solutions involving an open cooling system as well as dry and wet fan cooling towers, plant preparation for the future requirements for CO2 reduction. Thermal cycles of the analysed alternatives were modelled and analysed for a number of loads. As a result of the analyses, supercritical coal-fired units were recommended as optimum solution, for the location of Siekierki - 450 MWe net, for the location of Kawęczyn – 650 MWe.

EC Białystok S.A(E.On Group)
2006
Preliminary biomass contracting for Białystok CHP Plant. (approx. demand 200,000 t/a). Preparing letters of intent and a draft of long term biomass purchase agreement to secure interests of both parties, covering technical issues, quality assurance, price development and billing system, organisation and logistics etc. Letters of intent signed as a result of negotiations covered the supply of biomass of various origin in compliance with relevant Polish legislation.

Vattenfall Heat Poland
2005
Feasibility study of installing heat accumulator tank at Żerań CHP Plant, Warsaw
The study investigated the possibilities of incorporating a heat accumulator in the existing DH system at Żerań CHP Plant. Selection of optimal heat accumulator capacity was done in range of 10 000-40 000 m3. Economic analysis was made for a number of operation modes.

Vattenfall Heat Poland
2005
Technical and economic analysis of installing a steam engine at CHP Pruszków. A number of engine designs were analysed and economic analyses were made for the selected alternatives.

Zakłady Chemiczne Police S.A.
2005
Pre-project study evaluating economic viability of the projects involving modernisation of turbine-driven compressors of synthesis gas and CO2 turbine in the ammonia and urea production plant.

Radpec S.A.
2005

Full feasibility study of waste incineration plant construction in Radom, according to The National Fund for Environmental Protection and Water Management (NFOŚiGW) requirements. Analysis of waste fuel availability, including RDF and sludge; preliminary analysis of technical alternatives of the waste-to-energy plant, producing heat and power in cogeneration, including incorporation of heat accumulator with capacity of approx. 2000 m3.
Economic and financial analysis of the selected alternatives was conducted.

Vattenfall Heat Poland
2005
Feasibility study of installing heat accumulator tank at Siekierki CHP Plant, Warsaw
The study investigated the possibilities of incorporating a heat accumulator in the existing DH system at Siekierki CHP Plant. Analysed heat accumulator capacity was 15 000-40 000 m3. Economic analysis was made for a number of operation modes. Tender specification for heat accumulator technical design was prepared.
Project was realised and heat accumulator is operating since the 2nd quarter of 2009.

EC Białystok S.A.(E.On Group)
2005-2006
Feasibility study of boiler coal-to-biomass conversion at Białystok CHP Plant. The study consisted of analysis of the possibilities of supplying timber biomass to Białystok CHP Plant; technical-economic analysis of possibilities of conversion; financial analysis of the investment; environmental impact report to obtain environmental permits.

Atex Sp. z o.o.
2005
Preliminary feasibility study of a biomass-fired CHP project in Przemysl.


Elsam A/S
2005
Technical and environmental due diligence of WPEC Legnica as part of privatisation process.
WPEC Legnica supplies heat to Legnica and neighbouring towns as well as to Głogów and Lubin. The company has 3 heat plants (230MWt, 23MWt, 162MWt), 9 heat-only boiler plants of total capacity 33 MWt and a district heating network.
Technical status of equipment was assessed, and technical risks were identified. Risks related to legislation were evaluated, including environmental protection legislation. Local heat market was analysed.

Elsam A/S
2004

Preliminary feasibility study for a biomass fired CHP (20 MWe and 40 MWt) in the north of Poland.
The analysis covered a number of solutions for biofuels management and logistics. Feasibility of installing a flue gas condenser to recover heat for district heating was analysed as an additional option.

Elektrociepłownie Warszawskie
2003-2004

Study on EW S.A. (present VHP) development until 2020.
The work included analysis of development directions for VHP heat sources until 2020, taking into account internal conditions as well as the changing external factors (such as market conditions, environmental requirements etc.) For the purpose of the study, a uniform dynamic technical and economic model of all heat sources was prepared, including all VHP heat sources, split to generation units operating in Warsaw DH system (SPEC district heating network) and Pruszkow CHP. The model allows comparing the analysed development alternatives. The technical model included efficiency data of the existing and new equipment, minimum and maximum generation capacities of turbines and boilers, fuel parameters, emissions and furnace waste production, use of absorbent, water and other consumable media in the existing and new flue gas cleaning installation as well as a dynamic O&M model, taking into account operation hours, investment costs and O&M costs.
As a result of the work, possible investment alternatives were presented, including environmental installations for the existing facilities as well as construction of new generation facilities, such as new boilers, new coal-fired CHP units of various capacities, including a large supercritical unit, combined cycle CHP units of 60-250MWe at various locations, small biomass or multi-fuel CHP units. Basing on the prepared model of DH main lines, limitations of DH networks were analysed as well as the DH network modernisation and extension alternatives for the analysed options of heat allocation between heat sources. Feasibility of incorporation of heat accumulator (capacity 5000-20 000 m3) was also analysed.

Intercell S.A.
2003-2004

Concepts for long term energy supply to secure Intercell energy demand.
Technical condition of the equipment was assessed, and a concept of constructing a new industrial CHP plant of 50-100 MWe was presented. A number of fuel alternatives and technologies were analysed, using coal or natural gas as primary fuel. Each alternative included also applying waste biomass, sewage sludge and waste wood for power purposes. Possibility of connection to the national power grid was assessed.

Elektrownia Bełchatów S.A
2003
Turbine Hall Equipment Modernisation Concept Study for units 3-12 of Bełchatów Power Plant in 2007-2015. Technical condition assessment. Modernisation proposals taking into account available modern technologies and implications related to Poland joining EU.

Undisclosed Client
2002
Market analysis of the energy sector in Poland, including analyses of fuel market, power market and cogeneration market, as well as predictions of fuel and energy prices.

Elektrownie Szczytowo-Pompowe S.A.
2001
Concept of a 22 MW wind farm in Loznica, including feasibility study and a application for issuing development conditions.



INTERCELL S.A.
2001

Analysis of alternative heat supply for the paper factory by constructing an industrial CCGT plant (approx. 30 MWe and 140 MWt) or a gas-fired heat plant.

Łęczyńska Energetyka
Sp. z o.o.
2001
Feasibility study for an approx. 30 MWe CHP plant with CFB boiler at Bogdanka coal mine, based on coal slurry, waste coal, sludge from sewage treatment plant and municipal waste.


Legnica DH Company
2001

Verification of feasibility study for converting the municipal heat plant in Legnica into a CHP plant basing on the existing steam boilers, capacity of approx. 10 MWe.


Elektrownia Opole S.A.
2000-2001
Technical and economic assessment of “Technical conditions for Opole Power Plant connection to Opole municipality DH network” issued by ECO S.A
The analysis included influence of design temperatures, pressure and regulation method (quality or quantity) on feasibility of supplying 200 MWt heat from 18K360 turbine extractions to DH network of Opole by a planned DH pipeline of 9 km.

PAK Power Stations Group
1999

Ultra Super Critical steam parameters. Optimisation study for Pątnów II Power Project.



Undisclosed client
1998
Due diligence study for 10 MW windfarm project in Poland. Activities included production estimate for the windfarm, investment cost, energy pricing, ownership structure and assessment of the economy.

Kobo Sp. z o.o.
1998-1999
A feasibility study analysing construction of a CHP plant (30 MWe, 60 MWt) with fluidised bed boilers at Bogdanka coal mine, using waste coal from the mine.
The study also analysed the possibility to cover heat demand of neighbouring towns by the new CHP plant.

Energoinwest Białystok
1998-1999
Feasibility study for modernisation of Fasty CHP plant in Bialystok, covering usage of sludge from the municipal sewage treatment plant as fuel for the boilers of the CHP plant.
The feasibility study will cover technical solutions as well as economic and financial issues related to finding short term as well as long term solutions for the CHP plant and the municipal sewage treatment plant. Issues related to combustion of sewage sludge were an essential part of the study.

Chełm Zamojska Spółka Elektroenergetyczna Eastern Generation Ltd.
1998
Feasibility study of a CHP unit for the city of Chełm.
Analysed alternatives included a 60 MWe gas fired combined cycle plant, as well as 60 MWe coal fired CFB and PC boiler plants. The issue of utilising waste coal from the nearby Bogdanka coal mine was discussed in detail.



Opole Power Plant
1997-1998
Analysis researching the possibilities of introducing technical and organisational changes at Opole Power Plant, to improve and rationalise its operation. The coal﷓fired power plant consists of 4 equal units with a capacity of approx. 350 MWe and is one of Poland's most modern power plants. Technical benchmarking with Danish power plants.

Bełchatów II Power Plant Management
1997
Independent expert opinion for the study on super critical parameters and optimisation of unit capacity for Bełchatów II.


Kostrzyn Paper MillVattenfall Poland
Sp. z o.o.
1997
Feasibility study covering rehabilitation of an industrial CHP plant at Kostrzyn Paper Mill.
The study covered analysis of heat and power demand and a technical assessment of the existing equipment. The alternatives analysed included combined cycle alternative consisting of gas turbines and waste heat recovery boilers with supplementary firing, each with a capacity of 70 ton/h steam.
Preparation of full tender documentation for modernisation of the existing and erection of two new gas fired boilers.
Tendering procedure and selection of Contractor.

Elektrociepłownia Zielona Góra S.A.Danish Energy AgencyPartner: DPC.
1995 - 1998
Preliminary feasibility study for modernisation Zielona Góra CHP Plant. The project was grant supported by the Danish Energy Agency and co-financed by EC Zielona Góra.
The project included determining the heat, steam and electricity demand. A number of plant concepts were analysed such as biomass fired boiler and gas fired combined cycle plants. The use of domestic low calorific gas was analysed.
A combined cycle plant with a capacity on 100 MWe based on domestic gas was analysed in details covering technical, economic as well as financial matters including defining security package covering off-take contracts.


Zespół Elektrowni Ostrołęka
1994 - 1995
Feasibility study for modernisation of Ostrołęka A CHP plant.
The following alternatives were investigated: rehabilitation of existing CHP, district heating extraction from power plant Ostrołęka B, new coal fired CFB CHP, new combined cycle gas fired CHP. The coal fired CFB and the gas fired Combined Cycle plant were selected as the most attractive solutions and detailed financial analysis were prepared for these alternatives.

Zespół Elektrowni Ostrołęka
1995-1995
Pre-feasibility study of bark firing at Ostrołęka A CHP Plant.
The following alternatives were investigated: new multifuel CFB boiler, additional furnace to the existing boilers, new Bubbling Fluidized Bed (BFB) boiler, retrofit of the existing PC boiler to BFB bark firing boiler. The latter alternative was implemented.
ELSAMPROJEKT prepared investment package, and long-term fuel supply contract, implementation study, detailed tender specification, and contract with main contractor.

Polskie Sieci Elektroenergetyczne S.A.Danish Environmental Protection Agency
1993-1994

Technical Assistance to Polish Power Grid Company (PSE)
Preparation of a study "Potential of priority and CHP Development in Poland" for the Polskie Sieci Elektroenergetyczne (Polish Power Grid Company).
In 1992 PSE agreed with the World Bank to initiate a least cost plan for the development and rehabilitation of the Polish power plants. Part of this study is an analysis of the potential for development of cogeneration on the basis of existing and new power plants.

Powrót do początku strony