Vattenfall
Heat Poland
2010-2011,
2011- in progress |
Siekierki CHP boiler OP230 K-1
conversion to biomass fired BFB boiler. The project includes conversion
of the boiler and implementation of biomass handling systems with the
systems enabling deliveries of approx.. 320,000 t/a biomass by rail and
by road.
A feasibility study was prepared to determine the project concept. The
study analysed two solutions for boiler operation: common steam header
with other boilers or as a separate unit (boiler + turbine set).
Concept of flue gas condensing system and biomass handling (320,000 t/a
pellets) was described. Economic analysis of the project was made as a
basis for optimising project alternatives.
The scope of work also included preparation of environmental impact
report and an application for environmental permit and preparing an
application for land development conditions, including permitting
procedures and obtaining the said permits for the project.
The work also included preparation of tender documents (tender
specification, contract) for two tenders: to select unit modernisation
contractor and biomass handling system contractors, as well as
participation in the evaluation and selection of contractors.
|
ENERGA
Elektrownie Ostrołęka S.A.
2009 - in progress |
Preparing
the project of Ostrołęka C Power Plant construction (first unit approx.
1000 MWe). The scope of work included the Concept Study including
detailed feasibility study of the project and environmental
documentation, as well as materials for the tender to select the
Contractor for Ostrołęka C Power Plant construction.
As part of
feasibility study, construction of new power plant with 1000MW unit (PF
boiler fired with coal with up to 20% of biomass co-firing possibility)
with a cooling tower. A financial and economic analysis of the project
was made, as well as sensitivity analysis, risk analysis and business
plan for the project.
The work also included support for the Client in
the procedures related to the environmental decision for the
project.
The scope of work covers also preparation of full Tender
Specification (including draft Contract) for tendering procedure based
on Public Procurement Law (negotiated procedure with publication),
participation in negotiations and assistance for the Client during
entire tendering process.
|
PGE
Elektrownia Opole S.A.
2009-2011 |
Technical
consultancy in the tendering procedure to select the Contractor for
biomass handling system and biomass feeding installation in compliance
with Public Procurement Law, including also preparing Tender
Specification, tender evaluation and participation in negotiations.
As a
result of tendering procedure, the Contract was awarded.
|
DONG
Energy A/S
2009-2010 |
Owner’s
Engineer services during the construction of Karcino Wind Farm (51
MW).
The scope of work included preparing tender specification for EPC
Contract based on FIDIC for electrical and civil engineering part,
participation in negotiations with contractors and Owner’s
Engineer service for electrical and civil engineering part.
|
PGE EC
Rzeszów S.A.
2009-2010 |
Commercial,
legal and technical consultancy related to the selection of Contractor
for the construction of cogeneration unit based on vegetable oil fired
Diesel engines (electrical capacity of engines system – 25-30
MW).
The scope of work covered the complete tender documentation for
tender with negotiations (including Functional Programme and EPC
Contract), participation in the entire process of contractor selection
and advice in formulating optimum business solutions until signing the
contract.
The tendering procedure was conducted.
|
PKN
Orlen S.A.
2009 |
Preparing
implementation of the project „Construction of 2x420-460MW
near
Anwil S.A. area in Włocławek”.
The works included preparing
Feasibility Study analysing multiple alternatives for a two-phase
construction of two CCGT units. Construction alternatives were
presented. A closed cycle cooling system with cooling towers was
analysed as well as an open cooling system using the Vistula river
water. Technical and legal conditions for power plant construction were
prepared. A preliminary concept for power export and gas fuel supply
was presented, determining also the conditions of the local gas network
operator. Economic analysis of the alternatives was made, basing on
long term prices forecasts.
Guidelines for the Environmental Impact
Assessment were prepared. General Investment Costs Schedule was
prepared, together with the project budget. Project profitability
analysis was also implemented.
Technical Appendix to Tender
Specification for Turn-Key Delivery of CCGT Unit was prepared.
|
Vattenfall
Heat Poland
2008-2011 |
Participation
in tendering procedure to select EPC Contractor for Siekierki CHP unit
implementation.
The subject of tender is an extraction/condensing CHP
unit with an open cooling system, with a gross electrical capacity of
approx. 480 MW. The unit is to operate with the following steam
parameters: live steam not lower than 600°C and reheat steam
not
lower than 600°C. The unit will have a pulverized fuel boiler
fired
with hard coal (with biomass pellets co-firing possibility) with a
complex flue gas cleaning system. The unit will also produce heat for
Warsaw district heating system.
As part of the work, the unit concept
was optimised and Tender Specification for the unit was prepared,
covering technical, commercial and legal aspects for EPC project
implementation.
Tendering procedure based on Public Procurement Law was
conducted as negotiated procedure with publication. The scope of work
included cooperation with tender evaluation and participation in
negotiations.
As a result of tendering procedure, final bids were
submitted and evaluated.
|
Vattenfall
Heat
Poland
2006 |
FGD
plant for Siekierki CHP Plant in Warsaw.
The scope of work included
preparing a concept for FGD and a new chimney stack for Siekierki CHP,
for the existing coal-fired units and the planned new unit, including
analysis of several alternatives. The study compared the FGD concepts
based on wet lime technology, semi-dry method and dry method. As a
continuation of the conceptual work on multiple alternatives, a
detailed FGD concept for coal fired boilers at Siekierki CHP was
prepared.
Works included preparing the application and appendices for
the application for issuing construction conditions for the selected
alternative. Tender Specification was also made for FGD system with two
absorbers for 8 boilers, for 3.1 million Nm3/h, including functional
programme and the technical part of the contract with appendices
necessary for public procurement procedure.
FGD system at Siekierki is
currently under construction.
|
EC
Białystok S.A.(E.On Group)
2006 |
Preparing
tender specification for conversion of OP-140 boiler to a biomass fired
fluidised bed (BFB) boiler and implementation of biomass handling
system at Białystok CHP Plant.
|
J-Power
2006-2008
|
Zajączkowo
Wind Farm project. Services included preparing tender specification for
a wind farm in north-western Poland, consisting of 24 x 2MW. In the
implementation phase Elsamprojekt performed the function of
Owner’s Engineer.
|
Elsam
A/S
2006-2007 |
Ostrowo
Wind Farm project. Services include preparing tender specification for
a wind farm in north-western Poland, consisting of 17 x 1.8 MW wind
turbines, based on FIDIC and participation in negotiations with
contractors. In the implementation phase Elsamprojekt performed the
function of Project Manager and was responsible for Owners Engineer
services (electrical systems and civil works) and Project Management.
|
J-Power
2006 |
Due
diligence and review of documentation for a wind farm to be constructed
in northern Poland (Zajączkowo, 24x2MW),, carried out for the Investor
in order to provide a basis for the final decision on project
implementation.
|
Elana
Energetyka
2005
|
Technical
and economic audit at industrial CHP Plant Elana Energetyka to
formulate reorganisation guidelines. The audit included two CHP plants
fired with coal and heavy fuel oil (6 steam boiler with 4,5 MWe turbine
and 3 steam boilers with 20 MWe turbine), compressed air, cool,
nitrogen systems as well as water supply and sewage system.
As part of
the work, potential of the existing equipment was assessed and
rationality of the investments conducted and planned so far. Possible
development concepts and directions were prepared for modernisation
projects.
|
AES
Horizons Ltd.
2002
|
Involved
preparation of tender materials.
Involved in permitting procedures for a
250 MW CCGT project in Żarnowiec, Northern Poland.
|
Zielona
Góra CHP Plant
2001
|
Verification
of tender documentation for the second stage of tendering procedure for
a 190 MWe CCGT CHP plant in Zielona Góra.
|
EC
Białystok S.A.
2001 |
Verification
and preparation of tender materials for construction of a 20 MWe
condensing turboset at Bialystok CHP Plant.
Participation in tender
evaluation and selection of the Contractor.
The project is based on a
number of contracts (turbine set, DCS cooling tower, equipment
deliveries).
|
Elektrownia
„OPOLE” S.A.
2000
|
Tender
specification and offer evaluation for turbine modernisation and
preparation of heat extraction. For three 18K360 turbines with a
capacity of 360 MWe each.
|
Elektrociepłownia
Rzeszów S.A.
1999 |
Preparation
and verification of tender specification for EC Rzeszów CCGT
(95
MWe);
Tender evaluation.
Contract negotiations.
The tender was prepared
based on Public Procurement Law.
|
Zamojska
Spółka
Elektroenergetyczna Eastern Generation
1998
|
Preparation
of full tender documentation for turn-key project involving
construction of 100-120 MW CCGT plant in Jarosław. Participation in
negotiations with Polish Oil and Gas Company (PGNiG) and distribution
company.
|