ZEW Kogeneracja S.A.
2007-2008
|
Consulting services in the
preparation and implementation phase of the project involving biomass
co-firing system for Wroclaw CHP Plant unit 1, including analyses to
select the best technical and economic alternative. The selected
alternative included co-firing dry biomass (pellets) with approx. 45%
energy input, in a pulverised fuel boiler OP230 and a biomass handling
system with silos and biomass transport to the boiler. An environmental
impact report was prepared for the project, as well as an application
for project development conditions. Technical specification was
prepared for tendering procedure for the modernisation of boiler OP230
and construction of biomass handling system.The documentation prepared
made it possible to select contractors and conclude contracts for the
project implementation.
|
|
Vattenfall Heat Poland
2006
|
Preparing FGD plant concept
for Siekierki CHP Plant. A concept for FGD and a new chimney stack for
Siekierki CHP, for the existing coal-fired units and the planned new
unit, including analysis of several alternatives; preparing the
application and appendices for the application for issuing construction
conditions for the selected alternative; preparing tender
documentation, functional programme and the technical part of contract
specimen, necessary for public procurement procedure.
|
|
EC Białystok S.A.
2006
|
Preparing tender specification
for conversion of OP-140 boiler to a biomass fired fluidised bed (BFB)
boiler and implementation of biomass handling system at Białystok CHP
Plant.
|
|
Elsam A/S
2006-2007
|
Ostrowo Wind Farm project.
Services include preparing tender specification for a wind farm in
north-western Poland, consisting of 17 x 1.8 MW wind turbines. In the
implementation phase Elsamprojekt will perform the function of Project
Manager and will be responsible for Owners Engineer services
(electrical systems and civil works) and Project Management.
|
|
AES Horizons Ltd.
2002
|
Involved preparation of tender
materials.Involved in permitting procedures for a 250 MW CCGT project
in Żarnowiec, Northern Poland.
|
|
Zielona Góra CHP
Plant
2001
|
Verification
of tender documentation for the second stage of tendering procedure for
a 190 MWe CCGT CHP plant in Zielona Góra.
|
|
EC Białystok 4TG
2001
|
Verification
and preparation of tender materials for construction of a 20 MWe
condensing turboset at Bialystok CHP Plant.Participation in tender
evaluation and selection of the Contractor. The project is based on a
number of contracts (turbine set, DCS cooling tower, equipment
deliveries).
|
|
Opole Power Plant
2000
|
Tender specification and offer
evaluation for turbine modernisation and preparation of heat
extraction. For three 18K360 turbines with a capacity of 360 MWe each.
|
|
Rzeszów CHP Plant
1999
|
Preparation
and verification of tender specification for EC Rzeszów CCGT
(95 MWe);Tender evaluation.Contract negotiations.The tender was
prepared based on Public Procurement Law.
|
|
Zamojska Spółka
ElektroenergetycznaEastern Generation
1998
|
Preparation of full tender
documentation for turn-key project involving construction of 100-120 MW
CCGT plant in Jarosław. Participation in negotiations with Polish Oil
and Gas Company (PGNiG) and distribution company.
|