Vattenfall Heat Poland
2007-2008
|
Analyses regarding the
possibility of constructing a new CHP Plant in Grudziądz municipality
(kujawsko-pomorskie province). The report presents the concept of a
coal fired 2x800 MW ultra supercritical power plant with an open
cooling system (water from the Vistula), and alternatively with a
closed cooling system with a cooling tower. A preliminary layout of the
plant in the area indicated by the Employer was made. External
conditions for the project in the suggested location were analysed,
including connection to the HV power grid, connection to the road and
railway systems, possibilities to take in and discharge post-cooling
water, collisions with airway routes. A preliminary analysis of railway
and truck transport for the new power plant was made, including
agreements with the Polish Railway regarding the construction of a
railway siding. A preliminary geotechnical analysis of the location was
carried out to determine the conditions for building settlement. A
preliminary environmental impact assessment was made for the new power
plant, including Nature 2000 and other protected areas. Taking into
account the analyses specified above, a general investment budget was
prepared for the green-field project with all the accompanying
infrastructure in the analysed location.
|
|
Vattenfall Heat Poland
2007
|
Environmental impact
assessment report regarding wet desulphurisation plant for Siekierki
CHP Plant, preparing application for environmental decision, submission
of application to the relevant environmental authorities and
negotiations with the authorities. The project obtained environmental
decision for constructing the plant.
|
|
Bialystok CHP Plant
2007-
|
Owners Engineer. The project
involves construction of biomass plant for renewable power generation.
It includes PF coal fired boiler conversion into a bubbling fluidised
bed (BFB) boiler firing biomass similar to wood chips, and construction
of complete biomass handling system. Boiler capacity after
modernisation 105t/h steam; annual biomass consumption up to 200,000 t.
|
|
Vattenfall Heat Poland
2007-
|
Feasibility study of a biomass
fired CHP plant in Pruszków near Warsaw. A number of
technical and economic alternatives were analysed for the forecast heat
demand of approx. 250MWt. Plant capacities from 30 to 70MWe were
analysed in various configurations such as one unit with one boiler,
one unit with two boilers, or two units. The study also included
biomass market analysis and possibilities of organising energy crop
plantations.
|
|
Gdansk Heat Distribution
Company GPEC
2007
|
Feasibility study of a
cogeneration unit with municipal waste and biomass as main fuel. A
number of technical and economic alternatives were analysed for a
forecast heat demand of approx. 100MWt. Main alternatives included:
Waste-To-Energy project based on unsorted municipal wasted and
alternatively energy fraction separated from waste and a biomass
installation. Biomass types analysed included straw, pellets and wood
chips.
|
|
ZEW Kogeneracja S.A.
2007
|
Study of biomass generation
unit at ZEW Kogeneracja, aiming to find an optimum technical and
economic alternative for using biomass fuel for renewable energy
production at Wroc³aw and Czechnica CHP Plants.
|
|
Vattenfall Heat Poland
2006
|
Environmental impact report
for a project involving construction of a new 480 MWe unit at Siekierki
CHP Plant in Warsaw, prepared in order to obtain environmental permit
for the project. The report includes the environmental impact of the
entire Siekierki CHP Plant after implementing the new unit and the
planned environmental systems (flue gas desulphurisation and deNOx
plants).
|
|
Vattenfall Heat Poland
2006
|
Preparing FGD plant concept
for Siekierki CHP Plant. A concept for FGD and a new chimney stack for
Siekierki CHP, for the existing coal-fired units and the planned new
unit, including analysis of several alternatives; preparing the
application and appendices for the application for issuing construction
conditions for the selected alternative; preparing tender
documentation, functional programme and the technical part of contract
specimen, necessary for public procurement procedure.
|
|
Vattenfall Heat Poland
2006
|
Analysis of possibilities of
constructing new units in Poland; the study analysed location
conditions for construction of new coal fired and CCGT units, analysis
of the existing energy sources and local heat markets, selection of
optimal locations for new generation facilities.
|
|
Vattenfall Heat Poland
2006
|
Pre-feasibility study for a
construction of a new unit in Warsaw. The analyses covered multiple
alternatives of power units from 200 to 700 MWe, sub- and
supercritical, of varied heal output. Analyses were made for two
possible locations, at Siekierki CHP Plant and at Kaweczyn Heat Plant.
Technical and economic optimisation involved incorporation of new
facilities into the existing process systems, in compliance with the
present and future environmental requirements. The analyses took into
account a number of parameters and conditions influencing the optimal
selection of recommended alternative, such as combustion technologies,
steam parameters, thermal cycle of the plant, concept of district
heating part, various cooling solutions involving an open cooling
system as well as dry and wet fan cooling towers, plant preparation for
the future requirements for CO2 reduction. Thermal cycles of the
analysed alternatives were modelled and analysed for a number of loads.
As a result of the analyses, supercritical coal-fired units were
recommended as optimum solution, for the location of Siekierki - 450
MWe net, for the location of Kaweczyn - 650 MWe.
|
|
EC Bia³ystok S.A.
2006
|
Preparing tender specification
for conversion of OP-140 boiler to a biomass fired fluidised bed (BFB)
boiler and implementation of biomass handling system at
Bia³ystok CHP Plant.
|
|
EC Bia³ystok S.A.
2006
|
Preliminary biomass
contracting for Bia³ystok CHP Plant. (approx. demand 200,000
t/a). Preparing letters of intent and a draft of long term biomass
purchase agreement to secure interests of both parties, covering
technical issues, quality assurance, price development and billing
system, organisation and logistics etc. Letters of intent signed as a
result of negotiations covered the supply of biomass of various origin
in compliance with relevant Polish legislation.
|
|
J-Power
2006
|
Zaj¹czkowo Wind Farm
project. Services include preparing tender specification for a wind
farm in north-western Poland, consisting of 24 x 2MW. In the
implementation phase Elsamprojekt will perform the function of Project
Manager.
|
|
Elsam A/S
2006-
|
Ostrowo Wind Farm project.
Services include preparing tender specification for a wind farm in
north-western Poland, consisting of 17 x 1.8 MW wind turbines. In the
implementation phase Elsamprojekt will perform the function of Project
Manager and will be responsible for Owners Engineer services
(electrical systems and civil works) and Project Management.
|
|
J-Power
2006
|
Due diligence and review of
documentation for a wind farm to be constructed in northern Poland,
carried out for the Investor in order to provide a basis for the final
decision on project implementation.
|
|
Pekao Access
2006
|
Due diligence of
£añcut heat plant as part of privatisation process.
|
|
Vattenfall
2005
|
Feasibility study of
installing heat accumulator tank at ¯erañ CHP
Plant, WarsawThe study investigated the possibilities of incorporating
a heat accumulator in the existing DH system at
¯erañ CHP Plant. Economic analysis was made for a
number of operation modes.
|
|
Vattenfall
2005
|
Technical and economic
analysis of installing a steam engine at CHP Pruszków. A
number of engine designs were analysed and economic analyses were made
for the selected alternatives.
|
|
Police Chemical Plant
2005
|
Pre-project study evaluating
economic viability of the projects involving modernisation of
turbine-driven compressors of synthesis gas and CO2 turbine in the
ammonia and urea production plant.
|
|
Elana Energetyka
2005
|
Technical and economic audit
at Elana Energetyka to formulate reorganisation guidelines. The audit
included two CHP plants fired with coal and heavy fuel oil, compressed
air, cool, nitrogen systems as well as water supply and sewage system.
|
|
Radpec
2005
|
Full feasibility study of
waste incineration plant construction in Radom, according to National
Environmental Fund (NFOŒiGW). Analysis of waste fuel
availability, including RDF and sludge; preliminary analysis of
technical alternatives of the waste-to-energy plant, producing heat and
power in cogeneration - selection of the most attractive solution;
economic and financial analysis of the selected alternatives.
|
|
Bia³ystok CHP Plant
2005-
|
Modernisation and automation
project for Bia³ystok CHP Plant. Elsamprojekt is a Project
Manager for the entire project. Automation will be carried out at three
CHP units of EC Bia³ystok and will include auxiliary systems.
|
|
Vattenfall
2005
|
Feasibility study of
installing heat accumulator tank at Siekierki CHP Plant, Warsaw
The study investigated the possibilities of incorporating a heat
accumulator in the existing DH system at Siekierki CHP Plant. Economic
analysis was made for a number of operation modes. Tender specification
for heat accumulator was prepared.
|
|
BOT Elektrownia
Be³chatów S.A.
2005
|
Study on location of flue gas
desulphurisation plant for units 1 and 2, aimed to select a location
optimal form both economic and technical point of view
|
|
Bia³ystok CHP Plant
2005-2006
|
Feasibility study of boiler
coal-to-biomass conversion at Bia³ystok CHP Plant. The study
consisted of analysis of the possibilities of supplying timber biomass
to Bia³ystok CHP Plant; technical-economical analysis of
possibilities of conversion; financial analysis of the investment
|
|
Vattenfall
2005
|
Environmental due diligence of
Kozienice Power Plant, including necessary environmental investment
projects.
|
|
PCC AG
2005
|
Technical and market due
diligence of Kozienice Power Plant.
|
|
Vattenfall
2005
|
Environmental due diligence of
Bydgoszcz CHP Plant.
|
|
PCC AG
2005
|
Technical and market due
diligence for Ostroleka Power Plant Group.
|
|
Atex
2005
|
Preliminary feasibility study
of a biomass-fired CHP project in Przemysl.
|
|
Police Chemical Plant / Access
Ltd.
2005
|
Technical and market
due-diligence of Police industrial CHP plant for the Ministry of the
Treasury in the privatisation process.
|
|
Vattenfall
2005
|
Environmental due diligence of
Zabrze CHP Plant in the privatisation process.
|
|
Bialystok CHP Plant
2004
|
Preliminary feasibility study
of a project involving power production based on renewable energy
sources
|
|
Hedeselskabet Polska
2004
|
Development, negotiations and
assistance in signing renewable power sale agreements with three power
distribution companies.
|
|
Elsam A/S
2004
|
Preliminary feasibility study
for a biomass fired CHP (20 MWe and 40 MWth) in the north of Poland.
|
|
Elsam A/S
2004
|
Assessment of biomass
resources accessibility from forest areas and industry in north-eastern
Poland.
|
|
Rzeszow CHP Plant
2004-
|
LTSA for Rzeszów
CCGT Plant
The project includes preparing tender announcement and a complete
tender specification as well as tender evaluation, contract
negotiations and drafting a service contract in accordance with the new
Public Procurement Law.
|
|
Undisclosed Client
2003
|
Due diligence services for 37
MW CCGT project in Starachowice, review of fuel supply contracts, EPC
contract.
|
|
Warsaw CHP Plants
2003-2004
|
Study on EW S.A. (present VHP)
development until 2020. The work included analysis of development
directions for VHP heat sources until 2020, taking into account
internal conditions as well as the changing external factors (such as
market conditions, environmental requirements etc.) For the purpose of
the study, a uniform dynamic technical and economic model of all heat
sources was prepared, including all VHP heat sources, split to
generation units. The model allows comparing the analysed development
alternatives. The technical model included efficiency data of the
existing and new equipment, minimum and maximum generation capacities
of turbines and boilers, fuel parameters, emissions and furnace waste
production, use of absorbent, water and other consumable media in the
existing and new flue gas cleaning installation as well as a dynamic
O&M model, taking into account operation hours, investment
costs and O&M costs. As a result of the work, possible
investment alternatives were presented, including environmental
installations for the existing facilities as well as construction of
new generation facilities, such as new boilers, new coal-fired CHP
units of various capacities, including a large supercritical unit,
combined cycle CHP units of 60-250MWe at various locations, small
biomass or multi-fuel CHP units.
|
|
Rzeszow CHP Plant
2003-
|
Defect Liability Engineer
services for CCGT Rzeszow (100 MWe).
|
|
Intercell Paper Mill
2002-
|
Concepts for long term energy
supply to secure Intercell energy demand.
|
|
Belchatow Plant
2002-
|
Turbine Hall Equipment
Modernisation Concept Study for units 3-12 in 2007-2015. Technical
condition assessment. Modernisation proposals taking into account
available modern technologies and implications related to Poland
joining EU.
|
|
Lublin Wrotkow CHP Plant
2002-
|
Defect Liability Engineer
services for CCGT Wrotkow (235 MWe).
|
|
Lublin Wrotkow CHP Plant
2002-
|
Defect Liability Engineer
services for CCGT Wrotkow (235 MWe).
|
|
Elsam A/S
2002-2003
|
Owner's Engineer services
during the construction of Zagórze Wind Farm (30 MW).
Full Owner's supervision, verification of documentation, take-overs.
|
|
Elsam A/S
2002
|
Consulting services during
preparation, negotiations and conclusion of long-term power sale
contracts for renewable energy.
Consulting services for renewable energy sale in balancing market.
|
|
Elsam A/S
2002
|
Consultancy services during
negotiations of conditions of connecting to the power grid,
interconnection agreement and transmission agreement for 30 MW wind
farm.
|
|
Sydkraft
2002
|
Due diligence in STAR-PEC -
district heating company in Starogard Gdanski.
|
|
Undisclosed Client
2002
|
Market analysis of the energy
sector in Poland.
|
|
Undisclosed Client
2002-
|
Involved in sub-consulting
works related to preparation of bid materials and permitting procedures
for a large CCGT project in Poland.
|
|
Zielona Góra CHP
Plant
2001
|
Verification of tender
documentation (technical and commercial) for the second stage of
tendering procedure for a CCGT plant.
|
|
Elektrownie Szczytowo-Pompowe
2001-2002
|
Loznica Wind Farm feasibility
study
Feasibility study concerning the construction of a wind farm in the
north of Poland.
|
|
EC Bialystok 4TG
2001-2002
|
EC Bialystok extension -
adding a condensing turboset.
ELSAMPROJEKT together with ENERGOINWEST Bialystok prepared technical
specification for main components of the Project (turboset, cooling
tower etc.) and participated in Offer evaluation and selection of the
Contractor.
In the construction phase ELSAMPROJEKT will participate in the overall
Project supervision in the role of Owners Engineer.
|
|
Undisclosed Client
2001
|
Due Diligence in Zielona Gora
CHP.
EPPL provided consultancy engineering services for one of the potential
investors in a due diligence of Zielona Góra CHP Plant
(238MWt, 22.5Mwe, hard-coal fired) as part of privatisation process.
ELSAMPROJEKT scope included all the technical issues, such as
evaluation of the process systems at the plant, power and heat market
evaluation, cost and price structure analysis, development programme
analysis including the planned extension of CHP plant with a 190MWe
CCGT unit.
The job was performed for a foreign Client.
|
|
Undisclosed Client
2001
|
Due Diligence in a large
industrial CHP.
EPPL provided consultancy engineering services for one of the potential
investors in the preliminary phase of due diligence in an industrial
CHP plant to be outsourced from a large industrial plant. The CHP
plant, fuelled with hard coal , has a capacity of approx. 100 MWe and
approx. 200 MWt. ELSAMPROJEKT scope included evaluation of the process
systems, heat demand assessment, analysis of development possibilities
of the CHP plant in relation to the entire industrial plant.
The job was performed for a foreign Client.
|
|
Undisclosed Client
2001
|
Due Diligence in Gorzow
District Heating Company.
EPPL provided consultancy engineering services for one of the potential
investors in a due diligence of a heat distribution company as part of
privatisation process. Gorzow Heat Distribution Company (PEC) DH system
is the main heat supplier to the town of Gorzow Wielkopolski
(population of 126,000). The system is supplied from three heat
sources. Total demand for heat is approx. 140 MW, 1000 TJ/year. The
scope included technical part of due diligence, in particular
technology evaluation, heat market evaluation, development and
investment programme assessment, taking into account environmental
aspects.
The job was performed for a foreign Client.
|
|
Termall
2000
|
Pre-feasibility study for
construction of wind farm in Belchatow.
|
|
ELCHO Chorzow CHP Plant
Mott Macdonald
2000-
|
Owner's Engineer services for
two new coal-fired CHP units, 102 MWe each.
Responsibilities include site management, site supervisions, workshop
tests, commissioning, start-up, acceptance tests, contacts with Polish
Power Grid Company PSE. Full scope services for CFB boiler and steam
turbine.
|
|
Rzeszow CHP Plant
2000-2003
|
Owner's Engineer services for
new CCGT Rzeszow (105 MWe).
Responsibilities included site supervisions, workshop tests,
commissioning, start-up, acceptance tests of gas turbine and HRSG.
|
|
Lublin Wrotkow CHP Plant
2000-2002
|
Owner's Engineer services for
new CCGT Wrotkow (235 MWe).
Responsibilities included site supervisions, workshop tests,
commissioning, start-up, acceptance tests of gas turbine and HRSG.
|
|
Bank Pekao S.A.
2000-
|
Independent Technical Advisor
to the bank for the implementation of new CCGT Wrotkow (235 MWe).
|
|
Vattenfall Poland
2000
|
Assistance to a due diligence
team in connection with privatisation of GZE S.A. for one of potential
investors Site visits at HV/MV stations and MV/LV substations owned by
GZE.
|
|
Rzeszow CHP Plant
2000
|
Drafting of Service and
Maintenance Contract for new CCGT Rzeszow.
|
|
Gorzow CCGT Plant
2000
|
Drafting of Service and
Maintenance Contract.
|
|
Opole Power Plant
2000
|
Tender specification for
turbine modernisation and preparation of heat extraction. For three
18K360 turbines with a capacity of 360 MWe each.
|
|
PSE (Polish Power Grid
Company)
1999-2000
|
Report on development of
small-scale gas-fired cogeneration plants in European countries.
|
|
Ministry of the Treasury
Access Ltd.
1999
|
Participation in Wybrzeze CHP
Group (Gdansk) privatisation process.
Elsamprojekt's tasks included: Technical assessment and value
estimation of CHP buildings and equipment. Market analysis and
Wybrzeze's position, including power and heat price projection until
2010. Assessement of Wybrzeze technology as compared to Polish and
international conditions.
|
|
Vattenfall Poland Sp. z o.o.
1999
|
Technical Advisor in the
privatisation team for Warsaw CHP Plants (Elektrocieplownie Warszawskie
S.A.). Services included:
- Technical Due Diligence of the plants;
- Development potential forecast, including risk
evaluation;
- Collecting input data for the model of power
and heat production balance;
- Company structure assessment.
|
|
Rzeszow CHP Plant
1999-
|
Consultancy concerning bid
specification, EPC offers evaluation, contract negotiations
|
|
PAK Power Stations Group
1999
|
Ultra Super Critical steam
parameters. Optimisation study for Patnow II Power Project.
|
|
Zamojska Spolka
Elektroenergetyczna
Eastern Generation
1998
|
Technical Advisor for the
gasfired 100 to 120 MW Jaroslaw Combined Cycle Power Plant by Zamojska
Spolka Elektroenergetyczna (ZSE). ZSE is partly owned by the local
electricity distribution company ZKE and Eastern Generation from UK.
The plant will be located in the town of Jaroslaw in the south-eastern
part of Poland and is scheduled to go into commercial operation in year
2001.
The services supplied by ELSAMPROJEKT included preparation of EPC
Turnkey Project specification for the plant etc.
|
|
Enron
1998-
|
For the 120 MW industrial
combined cycle plant to be erected in Nowa Sarzyna by Enron,
ELSAMPROJEKT supports the investor with Site Manager and site
supervisors for the erection and commissioning of the plant.
|
|
Swe-Pol Link
1998-
|
The 300 MW HVDC project
between Poland and Sweden. Site supervision on behalf of the investor.
|
|
Kobo
1998-1999
|
Feasibility study analysing
the use of waste products from Bogdanka coal mine. The study analyses
the feasibility of using coal slurry in a new CHP plant, covering the
energy demand from the coal mine and for district heat from surrounding
cities. The study covers technical as well as economic and financial
aspects.
|
|
Belchatow II Power Plant
Management
1997
|
Independent expert opinion for
the study on super critical parameters and optimisation of unit
capacity for Belchatow II.
|
|
Kostrzyn Paper Mill
Vattenfall Poland Sp. z o.o.
1997
|
Preparation of feasibility
study and tender specification covering rehabilitation of existing and
erection of two new gas fired boilers supplying steam to existing back
pressure turbines and process steam to Kostrzyn Paper Mill.
Furthermore, a combined cycle alternative consisting of gas turbines
and waste heat recovery boilers with supplementary firing, each with a
capacity of 70 ton/h steam, was analysed.
The scope of work included heat/steam demand analysis, technical
assessment of existing equipment and preparation of tender
specification.
|
|
Zespol Elektrocieplowni
Bielsko-Biala SA
The European Bank for Reconstruction and Development
1994 - 1997
|
The project concerned the heat
and power company, Zespol Elektrocieplowni Bielsko-Biala SA, which in
the second half of the 1980s initiated the construction of a new heat
and power unit of 104 MJ/s heat and 55 MW power capacity. In 1991 the
project came to a halt due to financial difficulties. After an
evaluation of the project on behalf of the European Bank for
Reconstruction and Development in 1993 the bank decided to participate
in the financing of a completion of the project.
The plant was implemented on a turnkey basis. The erection took place
in the period 1995 to 1997. The consultant was responsible for
supervision of the project of behalf of EBRD.
|