J-Power
2006 |
Due
diligence and review of documentation for a wind farm to be constructed
in northern Poland (Zajączkowo, 24x2MW),, carried out for the Investor
in order to provide a basis for the final decision on project
implementation.
|
Karpacka
Spółka Gazownictwa S.A. / Pekao Access
2006 |
Technical
due diligence of Łańcut heat plant as part of privatisation process.
The
heat plant has 30 MWt thermal capacity in coal fired grate water
boilers and approx. 10 km of DH network.
Technical condition of heat
plant equipment was evaluated – as well as the need for
modernisation. Operation of the CHP plant was evaluated and the heat
sale was analysed. Alternative modernisation programmes were prepared.
Technical risk was evaluated.
|
Vattenfall
Heat Poland
2005 |
Environmental
due diligence of Kozienice Power Plant (coal fired units 8x200MW,
2x500MW), including necessary environmental investment projects.
Risk
related to adopted and planned environmental regulations were
identified and evaluated. Condition of the plant in terms of compliance
with current and future requirements of environmental protection.
Planned investments were assessed and the necessary investments were
indicated in the context of environmental protection.
|
PCC AG
2005 |
Technical
and market due diligence of Kozienice Power Plant. (coal fired units
8x200MW, 2x500MW) as part of privatisation process.
Technical evaluation
of Power Plant equipment was made and technical risks were identified.
Risks related to legislation including environmental legislation was
assessed. The power plant investment programme was assessed as well as
the position of the plant on the Polish market. Technical and economic
model of the plant was made and a proposal for the plant development
was drafted, including calculation of the power plant value based on
long term cash flow projection.
|
Vattenfall
Heat
Poland
2005 |
Environmental
due diligence of Bydgoszcz CHP Plant. The power plant group consists of
three CHP plants of respective capacities 187 MW/270MWt, 810MWt and
80MWt.
Risks related to current and planned environmental protection
requirements were identified and evaluated. The condition of
installation was assessed in terms of compliance with the current and
future environmental standards. Planned investments were assessed and
necessary environmental assessments were identified.
|
PCC AG
2005 |
Technical
and market due diligence for Ostroleka Power Plant Group (ZEO).
The
power plant group consists of a CHP Plant (75MWe/367MWt) and a power
plant (647MW). Technical condition of the power plant and CHP plant
equipment were assessed and technical risks were identified. Risks
related to legislation were assessed, including environmental
legislation. ZEO investment progress was evaluated. ZEO position in the
Polish market was estimated. A technical and economic model of ZEO was
prepared. A proposal of development was prepared together with a
calculation of ZEO value basing on long term cash flow projections.
|
Zakłady
Chemiczne Police S.A./ Access Ltd.
2005 |
Technical
and market due-diligence of power generation systems with two CHP
plants at ZCh Police for the Treasury as part of privatisation process.
CHP plants have 6 pulverised fuel boilers with a 38 MWe turbine and 2
PF boilers with a 64MWe turbine set.
As part of the works, also the
analysis of optimising the energy system of ZCh Police was made.
|
Vattenfall
Heat Poland
2005
|
Environmental
due diligence of Zabrze CHP Plant (106MW/595MWt) in the privatisation
process.
Risks related to current and planned environmental protection
requirements were identified. The condition of installations was
assessed in terms of compliance with current and future environmental
requirements. Planning was evaluated and necessary environmental
investments were identified.
|
Elsam
A/S
2005 |
Pre-feasibility
Study of a Biomass Fired CHP Plant (10-15 MWe with various cogeneration
ratios.
The analysis covered a number of solutions for biofuels
management and logistics. Feasibility of installing a flue gas
condenser to recover heat for district heating was analysed as an
additional option.
|
Elsam
A/S
2004
|
Due
diligence and appraisal of heating company in the north of Poland by
discounted planned cash flow method, taking into account extension of
the existing generation facilities with a biomass unit. The project
also included preliminary analysis as well as technical and economic
concept for the biomass unit located at the area of the existing
heating plant and connected to the municipal DH system.
|
Undisclosed
Client
2003 |
Due diligence services for 37 MW
CCGT project in Starachowice, review of fuel supply contracts, EPC
contract.
|
Intercell
S.A.
2003 |
Due-diligence of energy management
at the paper mill in Myszków.
|
Sydkraft
A/S
2002 |
Technical
due diligence in STAR-PEC – district heating company in
Starogard
Gdański.
The company has a heat plant of 58MWt and 16 local heat-only
boiler plants (HOB) of total capacity of 17MWt, as well as a DH network
of 21,5 km with 242 heat exchange nodes.
|
Undisclosed
Client
2002
|
Due diligence study investigating
the possibilities for a 30 MW wind farm project in Poland.
|
Undisclosed
client
2001 |
Due
Diligence in PEC Slupsk (Slupsk District Heating Company). ELSAMPROJEKT
provided consultancy engineering services for one of the potential
investors in a due diligence of a heat distribution company as part of
privatisation process. The company has two heat plants of 87MW and
74,5MW respectively, and 66 km DH network.
The job was performed for a
foreign Client.
|
Undisclosed
client
2001 |
Due
Diligence in a large industrial CHP.
ELSAMPROJEKT provided consultancy
engineering services for one of the potential investors in the
preliminary phase of due diligence in an industrial CHP plant to be
outsourced from a large industrial plant. The CHP plant, fuelled with
hard coal , has a capacity of approx. 100 MWe and approx. 200 MWt.
ELSAMPROJEKT scope included evaluation of the process systems, heat
demand assessment, analysis of development possibilities of the CHP
plant in relation to the entire industrial plant. The job was performed
for a foreign Client.
|
Sydkraft
A/S
2001 |
Due
Diligence in Gorzow District Heating Company.
ELSAMPROJEKT provided
consultancy engineering services for one of the potential investors in
a due diligence of a heat distribution company as part of privatisation
process. Gorzow Heat Distribution Company (PEC) DH system is the main
heat supplier to the town of Gorzow Wielkopolski (population of
126,000). The system is supplied from three heat sources. Total demand
for heat is approx. 140 MW, 1000 TJ/year. The scope included technical
part of due diligence, in particular technology evaluation, heat market
evaluation, development and investment programme assessment, taking
into account environmental aspects.
|
Elektrociepłownia
Zielona
Góra S.A.Sydkraft A/S
2001 |
Technical
Due Diligence in the CHP privatisation process, on behalf of
Sydkraft.
ELSAMPROJEKT provided consultancy engineering services for one
of the potential investors in a due diligence of Zielona
Góra
CHP Plant (238MWt, 22.5 MWe, hard-coal fired) as part of privatisation
process. ELSAMPROJEKT scope included all the technical issues, such as
evaluation of the process systems at the plant, power and heat market
evaluation, cost and price structure analysis, development programme
analysis including the planned extension of CHP plant with a 190MWe
CCGT unit.
|
Vattenfall
Poland
2000 |
Study
“Optimisation and development of Warsaw district heating
system”
In the study, strategic development directions for the
Warsaw district heating system were marked, in order to increase the
cogeneration ratio in Warsaw.
|
Vattenfall
Poland
2000 |
Assistance
to a due diligence team in connection with privatisation of GZE S.A.
for one of potential investors Site visits at HV/MV stations and MV/LV
substations owned by GZE.
|
Ministry
of the Treasury, Access Ltd.
1999 |
Participation
in Wybrzeże CHP Group (Gdańsk) privatisation process.
Elsamprojekt’s tasks included:
Technical assessment and value
estimation of CHP buildings and equipment.
Market analysis and
Wybrzeże’s position, including power and heat price
projection
until 2010.
Assessment of Wybrzeże technology as compared to Polish and
international conditions.
|
Vattenfall
Poland
Sp. z o.o.
1999 |
Technical
Advisor in the privatisation team for Warsaw CHP Plants
(Elektrociepłownie Warszawskie S.A.). Services of technical due
diligence included:
Technical Due Diligence of the plants;
Development
potential forecast, including risk evaluation;
Collecting input data for
the model of power and heat production balance;
Company structure
assessment.
|
Undisclosed
Client
1999
|
Technical due diligence of an
industrial CHP plant at the fat processing factory in Brzeg.
|