Vattenfall
Heat Poland
2010-2011,
2011- in progress |
Siekierki CHP boiler OP230 K-1
conversion to biomass fired BFB boiler. The project includes conversion
of the boiler and implementation of biomass handling systems with the
systems enabling deliveries of approx.. 320,000 t/a biomass by rail and
by road.
A feasibility study was prepared to determine the project concept. The
study analysed two solutions for boiler operation: common steam header
with other boilers or as a separate unit (boiler + turbine set).
Concept of flue gas condensing system and biomass handling (320,000 t/a
pellets) was described. Economic analysis of the project was made as a
basis for optimising project alternatives.
The scope of work also included preparation of environmental impact
report and an application for environmental permit and preparing an
application for land development conditions, including permitting
procedures and obtaining the said permits for the project.
The work also included preparation of tender documents (tender
specification, contract) for two tenders: to select unit modernisation
contractor and biomass handling system contractors, as well as
participation in the evaluation and selection of contractors.
|
ENERGA
Elektrownie Ostrołęka S.A.
2009 - in progress |
Preparing
the project of Ostrołęka C Power Plant construction (first unit approx.
1000 MWe). The scope of work included the Concept Study including
detailed feasibility study of the project and environmental
documentation, as well as materials for the tender to select the
Contractor for Ostrołęka C Power Plant construction.
As part of
feasibility study, construction of new power plant with 1000MW unit (PF
boiler fired with coal with up to 20% of biomass co-firing possibility)
with a cooling tower. A financial and economic analysis of the project
was made, as well as sensitivity analysis, risk analysis and business
plan for the project.
The work also included support for the Client in
the procedures related to the environmental decision for the
project.
The scope of work covers also preparation of full Tender
Specification (including draft Contract) for tendering procedure based
on Public Procurement Law (negotiated procedure with publication),
participation in negotiations and assistance for the Client during
entire tendering process.
|
PGE
Elektrociepłownia Gorzów S.A.
2009-2010 |
Technical
study of biomass installation at Gorzów CHP Plant.
The study of
OP-140 boiler conversion to biomass firing and construction of fuel
handling system at Gorzów CHP Plant to produce renewable
power.
The study includes different alternatives of biomass unit.
Alternatives with wet and dry biomass were analysed. Conversion of
existing PF OP-140 boiler from coal to biomass was analysed and new
boiler was taking in to consideration as an alternative. Thermal
calculations for the complete unit were carried out (boiler and
turbine).
|
El.
Rybnik S.A.(EDF Polska)
2009 |
Review
of technologies for biomass use in energy prodution and analysis of
application at Rybnik Power Plant in order to increase biomass
utilisation (Feasibility Study).
The objective of the study was to
determine best technical solutions enabling the increase of biomass
utilisation up to 700 000 Mg/a.
Multi-alternative concept analyses were
made, taking into account co-firing various biomass types with coal in
the existing unit boilers, as well as concepts of constructing a
dedicated biomass firing installation (new boilers, biomass gasifier).
Analyses covered biomass at different processing level, such as wet
biomass, dry biomass, torrefied biomass, liquid biomass, straw in
bales.
The study analysed issues related to biomass storage and
logistics, including the existing transport limitations. Analysis of
formal conditions for power to be qualified as renewable was made, as
well as the analysis of metering and billing issues.
|
Dalkia
Łódź S.A.
2009 |
Technical
and economic guidelines for converting OP230 boiler to a biomass fired
fluidised bed boiler at EC-4 CHP Plant in Łódź (biomass
consumption 370,000 t/a.).
A detailed concept of boiler conversion was
prepared with BFB furnace, technology of biomass combustion was
presented together with installation parameters. Influence of
modernised unit on the other Dalkia Łódź’s plants
was
analysed. Biomass transport and logistics assumptions as well as
biomass handling system were prepared.
Analysis of economic viability of
the project was carried out.
|
EC
Białystok S.A. (E.On Group)
2008 |
Concept
of a heat recovery system from flues gas condensation for a 75 MW
boiler fired with biomass (fuel humidity approx. 40%). The study
presented multiple alternatives for the 13-15 MW system consisting of a
scrubber and a condenser recovering head for district heating.
Technical solutions were presented as well as location and connection
of the heat recovery system with flue gas ducts, DH system and raw
water system. Technical and economic analyses were made, as well as
project profitability analyses, taking into account environmental
issues and grants.
|
Gdańskie
Przedsiębiorstwo Energetyki Cieplnej (Stadtwerke Leipzig)
2007 |
Feasibility
study of a cogeneration unit with municipal waste and biomass as main
fuel. A number of technical and economic alternatives were analysed for
a forecast heat demand of approx. 100MWt. Main alternatives included:
Waste-To-Energy project based on unsorted municipal wasted and
alternatively energy fraction separated from waste and a biomass
installation, as well as heat accumulator with capacity of approx. 8000
m3. Biomass types analysed included straw, pellets and wood chips.
|
ZEW
Kogeneracja S.A. (EDF Polska)
2007 |
Study
of biomass generation unit at ZEW Kogeneracja S.A.”, aiming
to
find an optimum technical and economic alternative for using biomass
fuel for renewable energy production at Wrocław and Czechnica CHP
Plants.
In the study functionality of heat accumulator with capacity of
2000-3000 m3 was examined mainly for levelling of irregularity of heat
consumption by green house.
|
EC
Białystok S.A(E.On Group)
2006 |
Preliminary
biomass contracting for Białystok CHP Plant. (approx. demand 200,000
t/a). Preparing letters of intent and a draft of long term biomass
purchase agreement to secure interests of both parties, covering
technical issues, quality assurance, price development and billing
system, organisation and logistics etc. Letters of intent signed as a
result of negotiations covered the supply of biomass of various origin
in compliance with relevant Polish legislation.
|
EC
Białystok S.A.(E.On Group)
2005-2006 |
Feasibility
study of boiler coal-to-biomass conversion at Białystok CHP Plant. The
study consisted of analysis of the possibilities of supplying timber
biomass to Białystok CHP Plant; technical-economic analysis of
possibilities of conversion; financial analysis of the investment;
environmental impact report to obtain environmental permits.
|
Atex
Sp. z o.o.
2005 |
Preliminary feasibility study of a
biomass-fired CHP project in Przemysl.
|
Elsam
A/S
2005 |
Technical
and environmental due diligence of WPEC Legnica as part of
privatisation process.
WPEC Legnica supplies heat to Legnica and
neighbouring towns as well as to Głogów and Lubin. The
company
has 3 heat plants (230MWt, 23MWt, 162MWt), 9 heat-only boiler plants of
total capacity 33 MWt and a district heating network.
Technical status
of equipment was assessed, and technical risks were identified. Risks
related to legislation were evaluated, including environmental
protection legislation. Local heat market was analysed.
|
Elsam
A/S
2004
|
Preliminary
feasibility study for a biomass fired CHP (20 MWe and 40 MWt) in the
north of Poland.
The analysis covered a number of solutions for biofuels
management and logistics. Feasibility of installing a flue gas
condenser to recover heat for district heating was analysed as an
additional option.
|
Intercell
S.A.
2003-2004
|
Concepts
for long term energy supply to secure Intercell energy demand.
Technical
condition of the equipment was assessed, and a concept of constructing
a new industrial CHP plant of 50-100 MWe was presented. A number of
fuel alternatives and technologies were analysed, using coal or natural
gas as primary fuel. Each alternative included also applying waste
biomass, sewage sludge and waste wood for power purposes. Possibility
of connection to the national power grid was assessed.
|
Zespół
Elektrowni
Ostrołęka
1994 - 1995 |
Feasibility
study for modernisation of Ostrołęka A CHP plant.
The following
alternatives were investigated: rehabilitation of existing CHP,
district heating extraction from power plant Ostrołęka B, new coal
fired CFB CHP, new combined cycle gas fired CHP. The coal fired CFB and
the gas fired Combined Cycle plant were selected as the most attractive
solutions and detailed financial analysis were prepared for these
alternatives.
|
Zespół
Elektrowni
Ostrołęka
1995-1995 |
Pre-feasibility
study of bark firing at Ostrołęka A CHP Plant.
The following
alternatives were investigated: new multifuel CFB boiler, additional
furnace to the existing boilers, new Bubbling Fluidized Bed (BFB)
boiler, retrofit of the existing PC boiler to BFB bark firing boiler.
The latter alternative was implemented.
ELSAMPROJEKT prepared
investment package, and long-term fuel supply contract, implementation
study, detailed tender specification, and contract with main
contractor.
|