Synthos
Dwory
Sp.
z o.o.
Oświęcim
2011 - in progress |
Modernisation programme for Synthos
Dwory CHP plant.
The work included preparing a concept for plant reconstruction in the
form of several alternative investment programmes based on
modernisation projects and construction of new coal or gas fired plants
as well as reserve and peak load sources fired with various fuels
(coal, natural gas, landfill gas, light fuel oil), several process heat
demand scenarios (CHP capacity from 250 to 700MWt) and unit operation
regime (full cogenetaion, partial condensing mode). Selection of the
optimum investment programme was made basing on the most profitable
process system, the fuel used and the reliability of heat supply to
Synthos Dwory.
|
Elektrociepłownia
EC Nowa Sp.
z o.o. (Tauron)
2011 |
Modernisation
concept for EC Nowa pumping systems.
The objective was to prepare an
optimum concept for the modernisation of the pumping systems at
industrial EC Nowa CHP Plant (120MWe, 1580 t/h steam), including
piping, metering systems, control and instrumentation and power supply,
in order to reduce power consumed by the pumping systems. The study
presents the results of energy audit of the pumping facilities and a
multi-variant concept of modernisation, indicating optimum solutions.
The analysis covered feed water pumps, cooling water pumps, district
heating water pumps and process water pumps. As a result of the study,
an economically feasible modernisation concept was proposed, resulting
in the total reduction of power consumption by approx. 32 GWh/a.
|
J-Power,
Zajaczkowo Wind Farm
2007 |
Preparation
of Wind Farm Operation and Maintenance Manual, including the
requirements for wind farm operator and power grid operator regarding
the division of equipment in terms of operation and maintenance,
operation of 110/30 kV substation and wind turbine, operation actions,
safety principles, co-ordination of operation and maintenance.
|
Zakłady
Chemiczne Police S.A.
2006
|
Concept
of fuel conversion from fuel oil to natural gas for selected systems of
Police Chemical Plant.
The work included technical and economic
analyses of multiple alternatives for fuel conversion from the
currently used mazout and light fuel oil to natural gas. Basing on the
economic analysis, which included investments costs, differences in the
fuel costs and in the related costs (such as operation costs,
environmental costs, maintenance costs), recommended alternatives were
presented.
|
BOT
Elektrownia Bełchatów S.A
2005-2006 |
Study
on location of flue gas desulphurisation plant for units 1 and 2, aimed
to select a location optimal form both economic and technical point of
view.
|
EC
Bialystok S.A.(SNET)
2004 |
Preliminary feasibility study of a
project involving power production based on renewable energy sources.
|
Starogard
Gdański
Polpharma
S.A./Vattenfall Poland Sp. z o.o.
1998
|
Co-operation
with Vattenfall in connection with commissioning of new fluidised
boilers at industrial CHP owned by Polpharma pharmaceutical plant.
|
ABB
Power
Generation, Baden,
Switzerland
1993 |
Technical
Assistance in connection with TEP1 at Turów Power Station.
In
cooperation with Ahlstrom PyroPower (USA) ABB Power Generation was
awarded the contract to rehabilitate up to six units of the Polish
lignite-fired 2000 MW power station in Turów. The
rehabilitated
units were supplied with new turbines/generators and new CFB boilers.
The capacity of each unit is 230 MWe.
Prior to the rehabilitation, a
Technical Evaluation Package (TEP1) was carried out in order to
determine how much of the existing installation could be reused under
the new conditions.
|